Greece: DEDDIE network saturation with many RES connections

Greek electricity distribution system operator DEDDIE had to turn down many applications due to network oversaturation. The operator is struggling to keep up with an increasing inflow of applications for connection to the distribution network by investors primarily behind solar energy projects.

This problem is mainly related to small-scale investments, which capacity is not enough to secure a transmission network connections via the transmission system operator ADMIE. Though the distribution operator has made considerable administrative progress it has not been enough to cope with the increased number of applications.

In the first half of 2020, DEDDIE responded, either positively or negatively, to a total of 1,500 connection term applications by RES investors representing a total of 580 MW. This is almost double compared to applications processed by DEDDIE in the second half of 2019 (730 applications with total output of 245 MW), and triple the number of applications processed in the first half of 2019 (520 applications, 165 MW).

According to DEDDIE, some 7,000 applications arriving from various parts of the country currently remain pending. Even at the increased pace, DEDDIE will require at least two years to get through these applications, along with the inflow of new application, many of which concerning energy communities, which are given priority.

 

 

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Greece approves €2.3bn programme for island grids, renewables and storage

Greece has secured approval for a €2.3 billion programme aimed at decarbonising its islands, with Athens directing more than €2 billion towards electricity interconnections, renewable generation and storage as it accelerates the replacement of oil-fired power. The approval was...

Metlen signs 10-year PPA for 12 MW Greek solar supply to Coca-Cola Tria Epsilon

Metlen Energy & Metals has signed a 10-year power purchase agreement to supply Coca-Cola Tria Epsilon with electricity from a new 12 MW solar project in Greece. The agreement is structured as a bilateral contract for long-term renewable power...

Greece wind buildout set to miss 2030 target despite faster 2026 additions

Greece accelerated wind-power construction in the first half of 2026, but projections indicate the country is still set to miss its 2030 capacity target. The outlook is based on figures cited in a document . Developers commissioned 321 MW...
Supported byVirtu Energy