EPCG tenders engineering and preparatory works for Krupac solar project

Engineering tender for preparatory construction

Montenegro’s state-owned utility EPCG has launched a tender connected to the development of the Krupac solar power plant. The procurement covers preparatory construction and engineering works related to the project. The contractor is expected to carry out initial activities valued at approximately €1.72 million. Bids are due by 10 July, and the selected contractor must complete the works within a maximum period of 180 days.

Scope within a broader preparatory phase

The tender forms part of a wider preparatory stage estimated at around €6.7 million. The planned activities are intended to prepare the groundwork for subsequent construction of the solar facility. Preparatory work is positioned as an early step ahead of the main development phase.

Planned site, capacity and expected generation

The future solar park will be located near Lake Krupac in the Nikšić region. The project area is described as approximately 118 hectares across three separate sites. Once operational, the planned plant capacity is 41.8 MW. It is expected to generate around 62 GWh of electricity annually.

Main design documentation preparation by Greener

EPCG awarded earlier this year a contract to the local engineering firm Greener for preparation of the main project design documentation. The resulting study is intended to support subsequent development phases and eventual construction of the facility. Earlier estimates place total investment in the Krupac solar power plant at about €28 million.

Renewables expansion in Montenegro’s electricity mix

The Krupac project is described as part of EPCG’s broader strategy to expand renewable energy capacity in Montenegro. It also aims to increase the share of solar power in the national electricity mix. The utility links the initiative to Montenegro’s long-term energy transition goals.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Montenegro electricity import bill below €42 million amid Italy interconnector plans

Montenegro has reduced its electricity-import bill to less than €42 million so far in 2026, according to energy officials. The improvement follows spending of almost €182 million during last year’s prolonged Pljevlja overhaul. Energy Minister Admir Šahmanović said the...

Montenegro grid-connection contracts for 3 GW highlight transmission and balancing needs

Montenegro has signed grid-connection contracts covering around 3 GW of renewable projects. The pipeline is described as several times larger than the country’s current peak demand. Transmission operator CGES said developers have expressed interest in about 7 GW of...

Perucica hydropower returns to full 307 MW after EPCG overhaul

Montenegro’s Perucica hydropower plant has returned to its full 307 MW capacity following the completion of the final stage of its annual overhaul by state utility EPCG. The restoration follows earlier partial grid return in early September, when 190...
Supported byVirtu Energy