Completion of overhaul on B2 unit of Power Plants Nikola Tesla Obrenovac

 

Completion of four month major overhaul project on Unit B2 of Power Plant Nikola Tesla (TENT) B in Obrenovac is about to be completed and its connection to the grid is expected on 10 september.

B2 overhaul is the biggest modernization project on TENT this year and is going within the plans and major work which influenced the time duration of the project is modernization and reconstruction of the electrostatic precipitator

This very complex project is financed mostly from EU donations, works realization is managed by polish Rafako who won on tender earlier and local partners are companies from Serbia, Gosa and Izoprogres.

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia, Montenegro power prices climb as Hungary-Germany spread narrows

Electricity prices in Serbia and Montenegro rose sharply for Tuesday delivery, moving against declines in Hungary and Romania as southeastern Europe’s reliance on imports increased despite stronger solar generation. The divergence highlights tighter local supply conditions in parts of...

Slovenia restarts Sostanj unit 5 to meet district heating demand

Slovenia’s Sostanj thermal power plant has temporarily restarted unit 5 as colder weather increases district heating demand. Unit 6 remains under maintenance while unit 5 is brought back into service. Heat demand has reached approximately 400 MWh a day. Unit...

E.ON Hungaria €625 million grid programme targets 2,323 MW connection capacity

E.ON is planning a €625 million expansion of its Hungarian grid. Separately, E.ON Hungaria is outlining a €625 million network investment programme aimed at adding 2,323 MW of connection capacity by 2030. The plan is intended to support additional...
Supported byVirtu Energy