Bulgaria: TPP Maritsa 3 narrows loss to €2.7 million in first half of 2025

Bulgarian thermal power plant Maritsa 3 reported a net loss of €2.7 million in the first half of 2025, a significant improvement compared to a €11.5 million loss during the same period in 2024.

The company’s total revenues fell to €6.65 million, down from €12.9 million in the first six months of 2024. Total expenditures also decreased substantially, reaching €9.3 million compared to €25.8 million last year.

Located in Dimitrovgrad, southern Bulgaria, TPP Maritsa 3 has a production capacity of 120 MW. Its largest shareholder is UK-based Topgroup, which holds a 49% stake.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Bulgaria electricity output up 15.6% in July as demand falls

Bulgaria’s electricity production rose 15.6% year on year to 3,779 GWh in July, while domestic consumption declined 4.1% to 2,652 GWh. The gap between output and demand widened over the month. Compared with June, generation increased 19.5%, while consumption...

Bulgargaz obtains 10-year wholesale gas licence for Serbia

Bulgargaz, the Bulgarian state-owned gas supplier, has secured a 10-year wholesale gas licence in Serbia. The permit authorises the company to conduct commercial gas trading on the Serbian market. The development extends Bulgargaz’s trading footprint across Southeastern and Central...

Kozloduy unit 5 output cut as Danube levels fall below cooling-water thresholds

Bulgaria’s Kozloduy nuclear power plant has reduced output from unit 5 after exceptionally low Danube levels constrained cooling-water availability. Regulators said the plant remains within safe operating limits. The reduction is linked to river conditions rather than an identified...
Supported byVirtu Energy