The rescue bill for TPP Maritsa is already reaching close to 500 million euros. Bulgaria continues to invest huge amounts in financially troubled coal-fired thermal power plant Marica East 2.

Last week, Bulgarian Energy Holding (BEH) bought the necessary greenhouse gas emission quotas for 2019 on behalf of the state-owned power plant. According to the company’s report, these amounted to a total of 156.5 million euros.

Including this amount, the state financing of TPP Maritsa East 2, which last year reported a loss of almost 110 million euros, approached 500 million euros, within less than three months. Thus, in early March, BEH decided to increase the capital of the thermal power plant by some 300 million euros, by converting part of the power plant’s debt to the parent company.

Although on the verge of bankruptcy, TPP Marica East 2 did not manage to reduce costs and high prices of produced electricity deprive it of the opportunity to participate in the free market. Despite that, the state is still persistently trying to artificially keep the thermal power plant alive, mainly for political reasons – the plant employs about 2,400 workers, while several hundred more are employed in the Maritsa East coalmine.

On the other hand, due to the continuous decline in electricity consumption in Bulgaria and connections with neighboring markets, the contribution of TPP Marica East 2 is currently very small – the power plant operates at about 25 % of capacity. Electricity produced by TPP Marica East 2 can easily be compensated by the production of US-owned coal-fired power plants AES’ Galabovo and ContourGlobal’s Marica East 3.

 

 

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Federation of Bosnia electricity generation up 15.8% in August as trade falls

Electricity production in the Federation of Bosnia and Herzegovina increased in August compared with August 2025, while both imports and exports declined from year-earlier elevated levels. Gross production reached 529 GWh, rising 15.8% from 457 GWh in August 2025....

Bulgargaz obtains 10-year wholesale gas licence for Serbia

Bulgargaz, the Bulgarian state-owned gas supplier, has secured a 10-year wholesale gas licence in Serbia. The permit authorises the company to conduct commercial gas trading on the Serbian market. The development extends Bulgargaz’s trading footprint across Southeastern and Central...

Kozloduy unit 5 output cut as Danube levels fall below cooling-water thresholds

Bulgaria’s Kozloduy nuclear power plant has reduced output from unit 5 after exceptionally low Danube levels constrained cooling-water availability. Regulators said the plant remains within safe operating limits. The reduction is linked to river conditions rather than an identified...