Bulgaria-Greece: Gas pipeline progress according to schedule

Gas interconnection between Bulgaria and Greece, so-called IGB pipeline, are progressing according to schedule, unaffected by the coronavirus outbreak. ICGB, is a joint venture company of Bulgarian Energy Holding (BEH) and IGI Poseidon, in which Greek Public Gas Corporation (DEPA) and Italian Edison hold equal stakes.

In January, Bulgarian Minister of Energy Temenuzhka Petkova said that the construction of gas interconnector will be completed in October this year. The delivery of the first batch of line pipes manufactured by Greek Corinth Pipeworks should be completed by the end of March.

Last May, ICGB awarded a contract for the construction of Bulgaria-Greece gas interconnection, so-called IGB pipeline, to Greek J&P-AVAX, which offered 144.85 million euros. The project company also awarded a supply line pipes contract worth 58.2 million euros to Greek Corinth Pipeworks Industry. In the first phase of the market test for IGB pipeline, nine companies have submitted non-binding expression of interest for the lease of gas interconnection between Bulgaria and Greece. The nine companies were: Bulgargaz, DEPA, Edison, SOCAR, Noble Energy, Gastrade, OMV Petrom, Citygaz and the Black Sea Technology Company. A total of 4.3 billion cubic meters per year was requested for gas transportation in Greece-Bulgaria direction, while around one billion cubic meters was requested in the opposite direction. The second phase, which was concluded in late 2016, produced five long-term bids while the announced capacity in the second phase of the market test amounted to 2.7 billion cubic meters, of which 1.57 billion cubic meters were reserved. 182 kilometers long Bulgaria-Greece gas interconnection is designed with the capacity between 3 and 5 billion cubic meters of gas per year, but it could be extended up to 10 billion cubic meters in case of commercial interest and economical justification. The construction of gas interconnection officially started on 22 May 2019.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

European gas rally lifts Bulgaria’s regulated September discount to €41.60/MWh

European benchmark gas prices moved above €74/MWh on Tuesday, widening the spread versus Bulgaria’s regulated September price of €41.60/MWh. The move highlights differences in fuel costs across Southeast Europe ahead of the autumn heating season. TTF rises as LNG supply...

Greece approves €2.3bn programme for island grids, renewables and storage

Greece has secured approval for a €2.3 billion programme aimed at decarbonising its islands, with Athens directing more than €2 billion towards electricity interconnections, renewable generation and storage as it accelerates the replacement of oil-fired power. The approval was...

Metlen signs 10-year PPA for 12 MW Greek solar supply to Coca-Cola Tria Epsilon

Metlen Energy & Metals has signed a 10-year power purchase agreement to supply Coca-Cola Tria Epsilon with electricity from a new 12 MW solar project in Greece. The agreement is structured as a bilateral contract for long-term renewable power...
Supported byVirtu Energy