Bulgaria, Country’s electricity transmission network in the 2022-2031 period developed by the system operator ESO

According to draft plan for the development of Bulgaria’s electricity transmission network in the 2022-2031 period developed by the system operator ESO, the gross electricity consumption in Bulgaria will not exceed 43,298 GWh by 2031.

Based on the current data, in 2031 the absolute maximum electricity load is expected to be 7,670 MW and the maximum load per average workday – 7,130 MW.

The forecast for the development of the gross national electricity consumption takes into account the estimates for the period until 2050 of the European Commission, the Sustainable Energy Development Agency, the Bulgarian Academy of Sciences, and the Ministry of Finance (regarding GDP).

In accordance with the investment intentions for the 2022-2031 period, it is planned to build 5,881 MW of electricity generation capacities, of which 4,858 MW in renewable energy. The share of energy from hydropower plants in electricity consumption is expected to reach up to 30 % in 2031.

The draft plan envisages new nuclear capacities in the 2030-2040 period. Even if such a project gets launched in 2022, it cannot be put into operation before 2032, which goes beyond the period covered by the report. Since the scale of these capacities is concentrated, and not decentralized like that of hydroelectric plants, their effect on the development of the electricity transmission network is significant and requires continuous pre- project research and coordination procedures.

Capacity balances show drastic disparity in the options for meeting domestic demand and possibly exporting electricity. In the winter season, it will not be possible to export electricity, and in some years it will even be necessary to resort to all available sources of additional services and/or electricity import. In the summer season, the possible export will depend on hydroelectric plants’ production, the draft plan shows.

According to ESO, the implementation of the plan for the electricity transmission network’s development until 2031 will provide the necessary security of electricity transmission in case of normal and repair schemes, including the necessary electricity exchange with neighboring countries.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

European gas rally lifts Bulgaria’s regulated September discount to €41.60/MWh

European benchmark gas prices moved above €74/MWh on Tuesday, widening the spread versus Bulgaria’s regulated September price of €41.60/MWh. The move highlights differences in fuel costs across Southeast Europe ahead of the autumn heating season. TTF rises as LNG supply...

Bulgaria approves sanctions exemptions for Kozloduy maintenance and Belene equipment preservation

Bulgaria has approved two targeted sanctions exemptions for Russia covering specific nuclear activities. The measures relate to maintenance-related work at the Kozloduy nuclear power plant and preservation activities for equipment stored at the unfinished Belene project. The exemptions keep...

Bulgaria September regulated gas price discount widens as TTF nears €74.4/MWh

Bulgaria’s regulated gas benchmark for September is trading at a widening discount versus European hub levels after Dutch front-month TTF climbed toward €74.4/MWh. The move has increased the gap between the Bulgarian price and the latest TTF assessment. The...
Supported byVirtu Energy