Bosnia: HPP Vranduk project stalled

The construction od hydropower plant Vranduk is currently on hold due to problems between the investor Bosnian power utility EPBiH and the contractor Strabag. Main reason for the stall is that the construction costs of the project have been exceeded. Strabag seeks to modify the project documentation in parallel with the construction, but the supervisory authority does not allow that.

According to Bosnian media, the construction costs are exceeded by some 6.5 million euros. In additions, EPBiH is dissatisfied because Strabag failed to complete the preparation of project documentation, to which supervisors have a number of objections. Therefore, Strabag suspended the works on the largest post-war energy investment in the Federation of Bosnia and Herzegovina (FBiH). EPBiH did not confirm this information, but did not deny it either.

The construction of the dam started without proper project documentation, which Strabag planned to develop in parallel to the construction. However, numerous objections by the supervisory authority have been placed, both currently and at the start of construction last year, which resulted in the fact that construction permit for the plant is still not issued. After the start of preparatory construction works last October, EPBiH said that they will subsequently apply for the construction permit, which should have been issued by February 2017. But, since project documentation for HPP Vranduk has not been completed, the permit has not been issued.

In January 2016, Bosnian power utility EPBiH has signed a contract worth 57.4 million euros with the joint venture of Austrian Strabag and Croatian Koncar. The signed turnkey contract includes the development of project documentation, production, delivery and installation of equipment, construction works and testing and commissioning of the plant. The construction of HPP Vranduk was officially launched on 8 September 2016.

According to the concession agreement from August 2012, EPBiH will design, build and operate the plant. The concession period will be 30 years, with extention option. EPBiH is obliged to pay onetime concession fee of 1.1 million euros, while annual concession fee will be 2.43 % of the annual income. HPP Vranduk will be built on Bosna river near Zenica and will have power output of 19.6 MW, while its annual electricity production should reach 97 GWh.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia drives Southeast European power price decline as renewables narrow regional spreads

Southeast European day-ahead electricity prices fell sharply for Wednesday delivery, as stronger wind and solar generation, improved domestic output and lower import requirements eased the supply pressure that had pushed regional markets well above Western European benchmarks a day...

Bulgaria launches 300 MWh Tesla battery project as energy storage expansion gains momentum

Bulgaria has begun construction of a 300 MWh battery energy-storage facility in Tvarditsa, marking the first stage of a broader investment programme worth more than €350 million. The programme includes three battery projects with a combined storage capacity of...

Bosnia and Herzegovina: ERS secures new loans as Ugljevik shutdown intensifies financial strain

Bosnia and Herzegovina’s state-owned power utility ERS has secured another €2 million in short-term financing, bringing the total amount of new borrowing arranged within just a few days to €7 million. The additional funds come as the company faces...
Supported byVirtu Energy