Bosnia and Herzegovina: Ulog hydropower plant faces issues during reservoir filling test phase

The Ulog hydropower plant near Kalinovik has entered the reservoir filling test phase, with a planned capacity of six million cubic meters. However, environmental organizations have reported issues at one-fifth of that capacity, including cracks and water leakage, which have raised concerns about potential larger problems.

In response, the investor, EFT Group, has paused the filling process, though the issues remain unresolved. Several environmental groups have appealed to institutions at all levels to address these concerns seriously.

Preparatory work for the plant began in 2011 but was interrupted for several years due to frequent landslides. Construction resumed in 2020. EFT Group holds a 30-year concession for the 35 MW HPP Ulog.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Republika Srpska accelerates generation and gas projects after drought curbs output

Energy and Mining Minister Petar Djokic said electricity production in Republika Srpska can normally run about 35% above domestic demand. He added that the buffer narrowed during summer due to dry weather cutting hydropower output. The Ugljevik thermal power...

Bosnia-Croatia southern gas interconnection delayed over financing and land issues

Agreement talks with AAFS Infrastructure & Energy Plans for the Southern Gas Interconnection between Bosnia and Herzegovina and Croatia remain delayed as developers work through financing, state-property and interstate-agreement issues. A planned agreement with US company AAFS Infrastructure & Energy,...

EU CBAM revisions could cut Bosnia electricity exporters’ costs by up to €13 million

Proposed changes to the European Union’s Carbon Border Adjustment Mechanism could reduce the cost faced by Bosnia and Herzegovina’s electricity exporters by as much as €13 million annually. Bosnia says the revisions could save exporters €13 million a year,...
Supported byVirtu Energy