TPP Ugljevik provides about a third of electricity in the Republic of Srpska.

Coalmine and thermal power plant (RiTE) Ugljevik, a subsidiary of Bosnian power utility ERS, urgently needs funds in order to stay liquid, therefore the management launched a tender for obtaining a loan worth 2.3 million euros from commercial banks.

Tender is divided into two lots, one for 1.3 million euros loan and the other for 1 million euros loan. For both loans, RiTE Ugljevik is prepared to pay servicing fees up to 80,000 euros and the loans should be repaid in 12 monthly installments. The deadline for submitting offers is 23 April.

RiTE Ugljevik recorded a net profit in the amount of some 760,000 euros in 2020, compared to a loss of 2.2 million euros in 2019. The company’s revenues in 2020 increased by 1.1 % year-on-year and amounted to 72.6 million euros, while its total expenditures rose by 0.8 % to 71.7 million euros. In late 2020, RERS approved 15 % higher purchase price of electricity for RiTE Ugljevik. According to initial estimates, annual revenues from electricity sales of RiTE Ugljevik will reach over 29 million euros, which is by some 3.5 million euros more than before. However, the producer’s initial request was not entirely fulfilled because they asked for an increase of 20 %.

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Republika Srpska accelerates generation and gas projects after drought curbs output

Energy and Mining Minister Petar Djokic said electricity production in Republika Srpska can normally run about 35% above domestic demand. He added that the buffer narrowed during summer due to dry weather cutting hydropower output. The Ugljevik thermal power...

Bosnia-Croatia southern gas interconnection delayed over financing and land issues

Agreement talks with AAFS Infrastructure & Energy Plans for the Southern Gas Interconnection between Bosnia and Herzegovina and Croatia remain delayed as developers work through financing, state-property and interstate-agreement issues. A planned agreement with US company AAFS Infrastructure & Energy,...

EU CBAM revisions could cut Bosnia electricity exporters’ costs by up to €13 million

Proposed changes to the European Union’s Carbon Border Adjustment Mechanism could reduce the cost faced by Bosnia and Herzegovina’s electricity exporters by as much as €13 million annually. Bosnia says the revisions could save exporters €13 million a year,...
Supported byVirtu Energy