Supported byClarion Energy
HomeElectricityBosnia and Herzegovina,...

Bosnia and Herzegovina, RiTE Ugljevik recorded a net profit in the amount of some 180,000 euros in 2020

Coalmine and thermal power plant (RiTE) Ugljevik recorded a net profit in the amount of some 180,000 euros in 2020, compared to a profit of 780,000 euros in 2020.

The company’s operating revenues in 2020 increased by 5.7 % year-on-year and amounted to 77.2 million euros, while its operational expenditures rose by 7.8 % to 78 million euros.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Federation of Bosnia electricity output rises 15.3% as coal production falls

Gross electricity production in the Federation of Bosnia and Herzegovina reached 534 GWh in September, up 15.3% from 463 GWh in September 2025. The rise came as domestic coal output continued to decline. Electricity generation increasingly relied on hydropower...

Bosnia’s August power output falls to 1,090 GWh as imports rise

Gross electricity generation in Bosnia and Herzegovina’s power sector totalled 1,090 GWh in August. That was down from 1,122 GWh a year earlier, as lower thermal output outweighed gains in hydropower and renewables. Thermal plants supplied 62.1% of gross...

Bosnia’s Ugljevik Restart Offers Relief as Power Tops €300/MWh

Bosnia’s Ugljevik thermal power plant is preparing to resume generation after emergency coal deliveries, easing pressure on the Republic of Srpska electricity system. The plant has been offline for more than two weeks, increasing reliance on costly wholesale imports....