The power plant Nikola Tesla B capital overhaul began on Unit B2

 

Another 620–megawatt generator in power plant “Nikola Tesla B“ from 14 May is outside of the power system, the realization of capital overhaul is underway.

In the next four months overhaul on B2 will be done through a very complex and extensive procedures. Among the most important activities is primarily the reconstruction of electrostatic precipitators ESP. That work is largely financed by donations from the European Union. The contract for part of the work financed by donations is entrusted to the Polish “Rafako“, with local companies sub-contractors “Gosa–assembly“ and “IZOPROGRES. The obligation of TENT is the creation of sedimentary electrode, supply transformers, removal of equipment and works on the key contributions of electrostatic precipitators. After reconstruction of the ESP on Unit 2, particulate emissions will be reduced to below 50mg/Nm3 in flue gas, which is in accordance with national and European norms.

In addition to standard operations, other capital repairs and reconstruction are planed: the grid for afterburning, slag system, replacement of superheater, inter heaters 1 and 3 as well as extensive alterations to the pneumatic transport of ash and slag in order to restore the equipment to the projected level and with minor modifications. Significant replacement on parts of the boiler pipe system will be implemented by “Feromont“ and “Termoelektro, a supplier of tubular elements is

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania: SANY acquires 153 MW battery project as €1 billion investment plan advances

Chinese industrial group SANY has acquired a 153 MW standalone battery-storage project in Borzești, Romania, strengthening its position in the country’s expanding renewable-energy and energy-storage market. The project was acquired from RNV Infrastructure, part of the Renovatio Group, through the...

Greece: PPC and Metlen to commission first 300 MW of regional battery capacity in early 2027

Greek energy groups PPC and Metlen expect to commission the first 300 MW of their joint battery-storage portfolio in the first quarter of 2027, with the initial projects located in Bulgaria and Romania. The facilities will mark the first operational...

Slovenia’s Mokrice hydropower plant could start construction in 2027-28

Construction of Slovenia’s long-delayed Mokrice hydropower plant could begin in late 2027 or early 2028, subject to permitting and possible legal challenges. The project would complete the chain of hydropower facilities on the lower Sava River. It is designed...
Supported byVirtu Energy