Statkraft has installed three additional floating solar units at Banja reservoir in southern Albania

Europe’s largest renewable energy producer Statkraft, in collaboration with Norwegian supplier Ocean Sun, has installed three additional floating solar units at Banja reservoir in southern Albania, bringing the floating solar plant’s total capacity to 2MW.

The installation of three additional floaters, rated at 500kW each, was completed during December 2022 as part of the second phase of the Banja project. The floating solar system is producing electricity according to expectations and confirms the positive results seen from the first floater, operational since April 2022.

In 2023, the 2MW system is expected to generate almost 3GWh of electricity. The plant represents Ocean Sun’s first multi-ring system and as such an important milestone for the company, demonstrating its ability to provide utility-scale projects.

In December 2018, Statkraft Renewables Albania filed a request to the Ministry of Energy and Infrastructure for a construction permit for a floating solar park, which was later obtained. After the installation of solar panels on the Banja reservoir, the company will consider similar plant at the Moglice reservoir.

Sign up for updates & special reports

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Croatia electricity generation up 13% in August 2026, imports still high

August 2026 generation mix and year-on-year increase Croatia’s electricity production rose 13% year on year to 1,262 GWh in August 2026, according to figures from the Croatian Bureau of Statistics. The data show output increasing from 1,117 GWh in August...

Albania: ALPEX electricity trading surges 76% in September amid regional market expansion

Electricity trading on the Albanian Power Exchange (ALPEX) increased sharply in September 2026, highlighting the continued development of organised wholesale electricity markets in Albania and the wider Southeast European region. Despite the strong annual growth, monthly trading activity declined...

Dalekovod secures €19.88 million contract for underground Tirana high-voltage substation

Contract award for Tirana Center substation Croatian power infrastructure company Dalekovod has secured a €19.88 million contract to develop a new underground high-voltage substation in Tirana, Albania. The facility is part of Southeast Europe’s expanding electricity transmission and distribution investment...
Supported byVirtu Energy