Supported byClarion Energy
HomeElectricitySlovenia: Court denied...

Slovenia: Court denied construction of HPP Mokrice

The Slovenian Administrative Court has ruled against the construction of the hydropower plant Mokrice. HPP was planned as the last one in a cascade on the Sava River.

The Slovenian Native Fish Society previously launched legal action against HPP Mokrice construction. It announced that the court ruled in favour of nature and the preservation of the Krka River’s mouth into the Sava River.

HPP Mokrice project envisages that the new 28.05 MW HPP should have a water inflow of 500 cubic meters per second and that its annual electricity generation should amount to 128 GWh.

The estimated cost of the project is around 177 million euros. The construction was supposed to start by the end of 2019. 45 MW HPP Brezice, the fourth of the five planned HPPs in the lower Sava project, was officially commissioned in 2017.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Slovenia net generation down 13% in August as imports increase

Slovenia’s net electricity generation fell 13% year on year in August to 919 GWh. Production was also 7% lower than in July. The month’s figures were accompanied by higher cross-border electricity movements. Conventional and nuclear output changes Thermal generation declined 42%...

North Macedonia generation drops 22% in July as renewables rise

North Macedonia’s gross electricity generation declined 22.3% year on year to 460,035 MWh in July, even as hydro and wind output increased. The month’s generation mix included higher contributions from hydropower and wind compared with the same period a...

Bulgaria generation up 11% on renewable growth through Sept. 20

Bulgarian electricity generation increased 11.33% year on year to 32.61 TWh between Jan. 1 and Sept. 20, with the rise supported by stronger renewable output. Domestic electricity consumption climbed 8.19% to 29.48 TWh over the same period. The resulting...
Supported byVirtu Energy