Supported byClarion Energy
HomeElectricitySerbia, Works on...

Serbia, Works on “Kostolac B-3” are coming to an end

On the construction site of EPS’s thermoblock “Kostolac B-3”, around 600 Chinese workers and more than 100 workers from Serbia are working intensively every day on the completion of this project.

– The number of workers at the location will grow and it is expected that a maximum of 1,100 will be hired at the end of July, said Željko Lazović, project manager. He added that more than 90 percent of installation work is expected to be completed by the end of the year. completed, writes Politika.

The volume of that work is evidenced by the fact that more than 2,500 piles were made, more than 90,000 m3 of concrete and more than 30,000 tons of steel construction were installed on the entire facility.

– The new thermoblock “Kostolac B-3” with a capacity of 350 MW is designed according to the strictest European standards and valid technical regulations. EPS’s investments in the thermal power plant “Kostolac B” enable the revival of domestic electrical and machine construction. The project included modern technologies and standards in the field of technology, then all currently valid elements of environmental protection, including some that are still pending. The contract also stipulates that all the equipment that will be installed in the new block meets European quality norms, Lazović said for Politika.

The expected annual production of this unit with a nominal capacity of 350 MW is about 2.5 billion kWh of electricity. Consent to the study on environmental impact assessment was obtained from the relevant ministry in October 2017.

– This project is very complex, so that a large number of renowned companies from the Republic of China are participating in its realization, and in addition to them, the Serbian economy is involved through many companies engaged in the production of equipment and works. Despite the measures taken to accelerate the implementation of the project, there are delays caused by the impact of the corona virus. All parties are continuously making an effort to reduce their effect on the realization of the project as much as possible, concluded Lazović, Blic reports.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia and SOCAR near joint venture for up to 500 MW gas-fired CHP

Serbia is close to setting up a joint venture with Azerbaijan’s SOCAR to develop a gas-fired combined heat and power plant. The planned facility would have capacity of up to 500 MW. The project is being advanced through negotiations...

Serbia’s power system recovery meets continued lignite dependence and rising project costs

Generation mix after earlier operational issues A 2025 energy-sector assessment says Serbia’s electricity system has recovered from severe operational problems earlier in the decade, but the sector remains exposed to further shocks. Continued reliance on lignite, higher infrastructure costs and...

Serbia maintains power price advantage as volatility challenges export potential

Serbia maintained one of the more competitive wholesale electricity positions in Southeast Europe during the second half of August, supported by stronger hydro, renewable and thermal generation. However, the sharp increase in prices at the beginning of September demonstrated...
Supported byVirtu Energy