Serbia, Works on “Kostolac B-3” are coming to an end

On the construction site of EPS’s thermoblock “Kostolac B-3”, around 600 Chinese workers and more than 100 workers from Serbia are working intensively every day on the completion of this project.

– The number of workers at the location will grow and it is expected that a maximum of 1,100 will be hired at the end of July, said Željko Lazović, project manager. He added that more than 90 percent of installation work is expected to be completed by the end of the year. completed, writes Politika.

The volume of that work is evidenced by the fact that more than 2,500 piles were made, more than 90,000 m3 of concrete and more than 30,000 tons of steel construction were installed on the entire facility.

– The new thermoblock “Kostolac B-3” with a capacity of 350 MW is designed according to the strictest European standards and valid technical regulations. EPS’s investments in the thermal power plant “Kostolac B” enable the revival of domestic electrical and machine construction. The project included modern technologies and standards in the field of technology, then all currently valid elements of environmental protection, including some that are still pending. The contract also stipulates that all the equipment that will be installed in the new block meets European quality norms, Lazović said for Politika.

The expected annual production of this unit with a nominal capacity of 350 MW is about 2.5 billion kWh of electricity. Consent to the study on environmental impact assessment was obtained from the relevant ministry in October 2017.

– This project is very complex, so that a large number of renowned companies from the Republic of China are participating in its realization, and in addition to them, the Serbian economy is involved through many companies engaged in the production of equipment and works. Despite the measures taken to accelerate the implementation of the project, there are delays caused by the impact of the corona virus. All parties are continuously making an effort to reduce their effect on the realization of the project as much as possible, concluded Lazović, Blic reports.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Djerdap 3 pumped-storage: Bechtel-Enka qualifies as Serbia prepares planning

Serbia has advanced work on the proposed Djerdap 3 pumped-storage hydropower project, with a Bechtel-Enka consortium qualifying for the next stage of government negotiations. At the same time, a Serbian engineering consortium is preparing the project’s planning framework. The...

Domestic industrial PPAs open new revenue opportunities for Serbian and Montenegrin renewables

Domestic industrial demand can support renewable investment and improve electricity cost predictability, but the carbon value of a power purchase agreement depends on the products being exported and the emissions rules governing them. Renewable developers in Serbia and Montenegro have...

Serbian renewable projects face new contractual challenges on the Hungary export corridor

Export PPAs can expand market access for wind and solar projects, but the revenue ultimately reaching developers depends on delivery rights, trading costs and the share of output that qualifies for actual-emissions treatment. Serbian wind and solar developers targeting Hungarian...
Supported byVirtu Energy