Serbia’s Banatski Dvor underground gas storage expansion is experiencing further slippage, according to project timelines that have moved past the previously targeted end of 2026. The delay increases the need for additional storage capacity outside Serbia. Serbia rents about...
Hungary has received temporary approval from the European Commission to postpone full implementation of EU gas-capacity rules at its border with Serbia until the 2027/2028 gas year. The derogation relates to requirements that cross-border pipeline capacity be offered as...
Serbia has secured a $600 million World Bank framework for a gas-system overhaul. The programme is planned as a decade-long modernisation of Serbia’s gas network. It covers pipelines, underground storage and institutional reforms.
Financing and initial pipeline focus
The first phase...