Serbia: Over 85 % of preparations for the construction of TPP Kostolac unit B3 completed

According to Serbian newspapers, the preparations for the project for the construction of a new unit B3 at coal-fired thermal power plant Kostolac, a project worth 613 million dollars, are over 85 % completed.

The Investment Portfolio Manager at Serbian state -owned power utility EPS Zeljko Lazovic said that the project is split into 14 phases and carried out in three directions: preparation of project documentation and obtaining of permits and authorizations, preparation and delivery of equipment and execution of works. So far, eight building permits have been obtained, which is more than 85 % of the project, which opens the possibility of carrying out substantial works at the construction site. Once the documentation is prepared and the permits are obtained, the construction of the unit B3 will begin.

The construction of the third unit is part of the second phase of a project for the modernization of Kostolac B at a total cost of some 712 million dollars. The construction of unit B3 will cost 520 million euros and it will produce 2.5 billion kWh of electricity per year, thus boosting EPS’ production capacity by some 5 %. Implementation of the project for the modernization of TPP Kostolac B was officially launched in January 2016, when EPS made an advance payment to the contractor, China Machinery Engineering Corporation (CMEC). In order to finance this project, EPS obtained a preferential loan from Chinese Exim Bank. The maturity of the loan is 20 years, with a 7-years grace period and fixed interest of 2.5 %. The deadline for the completion of the new unit is five years (until the end of 2020), and since the grace period lasts for another two years the idea is that the unit will partially repay itself if electricity production starts on time.

Kostolac TPP complex consists of two power plants – TPP Kostolac A (unit A1 and unit A2, 310 MW in total) and TPP Kostolac B (unit B1 and B2, 700 MW in total), including Drmno mine which supplies coal for all units.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Djerdap 3 pumped-storage: Bechtel-Enka qualifies as Serbia prepares planning

Serbia has advanced work on the proposed Djerdap 3 pumped-storage hydropower project, with a Bechtel-Enka consortium qualifying for the next stage of government negotiations. At the same time, a Serbian engineering consortium is preparing the project’s planning framework. The...

Domestic industrial PPAs open new revenue opportunities for Serbian and Montenegrin renewables

Domestic industrial demand can support renewable investment and improve electricity cost predictability, but the carbon value of a power purchase agreement depends on the products being exported and the emissions rules governing them. Renewable developers in Serbia and Montenegro have...

Serbian renewable projects face new contractual challenges on the Hungary export corridor

Export PPAs can expand market access for wind and solar projects, but the revenue ultimately reaching developers depends on delivery rights, trading costs and the share of output that qualifies for actual-emissions treatment. Serbian wind and solar developers targeting Hungarian...
Supported byVirtu Energy