Serbia: New TPP Kostolac unit construction to start 3Q 2015

Director of the company Thermal Power Plants and Mines Kostolac Goran Horvat said today that construction of new unit B3 is scheduled to begin in the second half of 2015th, but before that Electric Power Industry of Serbia (EPS) must pay an advance of 100 million dollars.

He stated that EPS provided the money for the job, but that the money has not been paid because of the ongoing reorganization of the public enterprises.

The new unit in thermal power plant Kostolac should be connected to the grid by 2020th, with the strength of 350 MW, and Chinese Exim Bank has provided a loan of for its construction. By this loan it will be also financed the expansion of capacities of open pit mine “Drmno” in the second phase, with nine million to 12 million tons of coal annually.

The units B1 and B2 were revitalized in the first phase of the capacities expansion of TPP Kostolac, and soon will begin the units’ desulphurization and construction of railway line to transport ore. The total works value in the first two phases was1.2 billion dollars.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

North Macedonia targets 2027 construction start for €1.5 billion Čebren-Galište hydro project

North Macedonia is targeting a 2027 construction start for the long-planned Čebren and Galište hydropower projects, reviving a combined investment of up to €1.5 billion after years of unsuccessful concession attempts. Čebren is planned with a capacity of around 333...

Greek court shuts solar permitting loophole after 185 MW project ruling

Greece’s highest administrative court has overturned approvals for a 185 MW solar development that had been divided into dozens of smaller projects, potentially tightening permitting requirements across the country’s utility-scale photovoltaic pipeline. The Council of State cancelled 186 preliminary producer...

Romania backs 1.3 GW Dama Solar project with €561 million financing

Romania has secured up to €561 million in financing for the 1.3 GWp Dama Solar project, clearing the way for construction of one of Europe’s largest onshore renewable-energy developments. Developer Rezolv Energy said the syndicated financing involves 14 lenders, with...
Supported byVirtu Energy