Romania: Termination of contract for TPP Iernut issues

Spanish company Duro Felguera, the leader of the consortium that was supposed to build the 430 MW gas-fired unit at thermal power plant Iernut for Romanian natural gas company Romgaz, said that the termination of the contract by the Romanian company does not comply with the contractual terms and conditions, adding that it reserves the right to initiate legal action in defense of its interests.

According to Romanian media, such legal actions are already activated because the termination of the contract activates Duro Felguera’s court action (initiated in April) aimed at deferring the deadline and preventing the loss of the 25 million euros guarantee. The consortium says that it maintains its willingness to complete the works on the project, given the overall completion is at 94 % and Duro Felguera completed 98 % of its part.

After five extensions of negotiation period, Romgaz has finally terminated the contract concluded with a consortium of Spanish Duro Felguera and local Romelectro for the construction of a gas unit at thermal power plant Iernut. The termination comes two and a half months after Romgaz initially announced the imminent termination of the contract signed in 2016 with the consortium.

In November 2016, Romgaz has concluded an agreement worth 268 million euros (without VAT) with a consortium of Spanish company Duro Felguera and Romanian Romelectro for a turnkey project for the construction of new 430 MW gas-fired power plant within its Iernut thermal power plant. The deadline for the completion of the new combined cycle power plant is 36 months from the effective date of the contract, which shall be within 5 working days from the date the NIP financing is approved. Romgaz took over Iernut thermal power plant in 2013 from Bucharest-based thermal energy producer ELCEN in exchange for deleting a 145 million euros debt. Initially, the plant was supposed to be commissioned in early 2020, but delays have arisen, both as a result of disagreements between partners regarding the provisions of GEO 114/2018 and regarding the increase in construction costs.

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania expands flexibility market as industrial demand and telecom batteries enter power system

Romania is beginning to turn electricity demand and previously underused backup infrastructure into tradable flexibility, creating new opportunities for aggregators and virtual power plants across Southeast Europe. Two developments illustrate the shift. Transmission system operator Transelectrica activated Romania’s first balancing...

Romania’s power imports surge as renewable generation declines

Romania’s net electricity imports surged 82.08% to 135.72 GWh in the week ending 20 September, as weaker renewable and hydropower generation increased the country’s reliance on electricity from neighbouring markets. Wind and solar generation in Romania fell by 25.9%, while...

Cernavoda output loss expected to continue into October amid low Danube levels

Romania is expected to remain without output from the Cernavoda nuclear plant into October as low Danube levels continue to restrict cooling conditions. The prolonged outage is occurring during a tight regional power market, with increased reliance on cross-border...
Supported byVirtu Energy