Supported byClarion Energy
HomeSEE Energy NewsRomania: Tender for...

Romania: Tender for the feasibility study for the connection of a 40 MW solar power plant launched

Romgaz, a natural gas producer, launched a tender for the procurement of a feasibility study for the connection of a solar power plant to the national electricity network.

A company is planning to build a solar power plant with installed capacity of up to 40 MW in Mures county.

The deadline for non-binding submissions is 25 August.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania delays Cernavodă restart amid Danube drought, extending nuclear outage

Romania is unlikely to restart either reactor at the Cernavodă nuclear plant for at least another 10 days, pushing recovery beyond mid-September. The delay extends the loss of around 1.3-1.4 GW of baseload generation and keeps Romania reliant on...

Rompetrol Rafinare boosts Petromidia storage capacity amid refinery upgrade

Rompetrol Rafinare is expanding storage capacity at its Petromidia refinery as part of a programme aimed at improving the flexibility and reliability of crude oil and fuel logistics. The company’s works include changes to tank capacity and refurbishment across...

Romania emergency Danube measures for cooling-water supply at Cernavoda

Three-stage plan tied to intake basin water level Romania has approved an emergency intervention plan aimed at maintaining cooling-water supplies for the Cernavoda nuclear power plant amid exceptionally low Danube levels. The measures would be triggered if the water level...
Supported byVirtu Energy