Romania, OMV Petrom has successfully completed the transport of four coke chambers to the Petrobrazi refinery

OMV Petrom has successfully completed the transport of four coke chambers to the Petrobrazi refinery. They will be operational in 2023 and will replace those in operation since 1989. The total investment for the replacement of coke chambers is 70 million euros, of which 25 million has already been invested.

Member of the OMV Petrom Board of Directors responsible for Refining and Marketing Radu Caprau said that the replacement of the coke chambers is an essential project for the Petrobrazi refinery. The investment in this project will improve the efficiency and safety of the refinery’s operations. The coke chambers will be replaced during the two-month overhaul planned for the first half of 2023.

Coke chambers have an essential role in the refining process, ensuring, at high temperatures, the transformation of heavy components into superior products. The weight of a coke chamber is almost 200 tons, the diameter is about 6 meters, and the height is about 30 meters. They were produced in Romania, in Bucharest.

Petrobrazi refinery has a total crude oil processing capacity of 4.5 million tons per year. Since 2005, OMV Petrom has invested over 1.8 billion euros in the Petrobrazi refinery, a third of this investment contributing to the reduction of the impact on the environment.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania extends 25% diesel excise reduction until Oct. 31

Romania will keep a 25% reduction in diesel excise duty until Oct. 31, extending temporary relief for transport operators and other businesses. The decision follows a period in which international fuel-market prices have risen faster than domestic pump prices....

R.Power completes 55-MW Lazuri solar plant in Romania; grid link by end-2026

Polish renewable-energy developer R.Power has finished construction of the 55-MW Lazuri solar plant in Romania’s Satu Mare county. Grid connection is expected before the end of 2026. The project is forecast to produce around 70 GWh annually, equivalent to...

Transelectrica to invest over €2.25bn in Romania grid upgrades through 2035

Romanian transmission system operator Transelectrica plans to invest more than €2.25 billion between 2026 and 2035 as part of a ten-year grid programme. The plan prioritises international interconnectors, completion of the domestic 400-kV transmission ring, and renewable integration. The...
Supported byVirtu Energy