Reservoir Capital provides a progress report on its 58.4 MW Brodarevo Hydroelectric Project in southwest Serbia

 

Reservoir Capital Corp. provides a progress report on its 58.4 MW Brodarevo Hydroelectric Project on the River Lim in southwest Serbia, where the Company is completing Feasibility Studies.

Zigma A.D. Niksic (“Zigma”), of Podgorica (Montenegro) under the supervision of the Company’s main contractor Energoprojekt Hidroinzenjering Co. Ltd. (“Energoprojekt”) and the Mining and Metallurgy Institute of Boris undertaking geotechnical drilling and sampling at Brodarevo. One drill rig started in early July, with a second added subsequently to accelerate the drilling program, which should be completed by month end. The program aims to test the geotechnical properties of the sediments and bedrock both in the river and the river banks to assist in the final designs for the Brodarevo dam foundations and infrastructure.

Testwork was completed in July on the 1:40 scale hydrological models of the Brodarevo dams constructed at the Brodarski Institut d.o.o. in Zagreb (Croatia); measuring the performance of the design of the dams and related structures under both optimal and severe (flooding) energetic and hydraulic conditions to assess safety, environmental and economic considerations. The testwork, supervised by Energoprojekt and Tractebel Engineering S.A., generated various design improvements, notably for the river diversion and spillways, which will be incorporated into the final design.

Environmental studies in accordance with Serbian standards and legislation are being conducted in parallel with studies according to World Bank guidelines. Both sets of studies are being conducted by Energoprojekt and are on schedule for completion in October 2011.

The design, environmental studies and permitting for the sections of the M-21 road affected by the Brodarevo Project have been contracted to Put Inzenjering (“PUT”) of Podgorica (Montenegro). PUT has completed detailed surveys and design work and will be undertaking geotechnical drilling over the coming weeks.

Source balkans.com

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania: SANY acquires 153 MW battery project as €1 billion investment plan advances

Chinese industrial group SANY has acquired a 153 MW standalone battery-storage project in Borzești, Romania, strengthening its position in the country’s expanding renewable-energy and energy-storage market. The project was acquired from RNV Infrastructure, part of the Renovatio Group, through the...

Greece: PPC and Metlen to commission first 300 MW of regional battery capacity in early 2027

Greek energy groups PPC and Metlen expect to commission the first 300 MW of their joint battery-storage portfolio in the first quarter of 2027, with the initial projects located in Bulgaria and Romania. The facilities will mark the first operational...

Slovenia’s Mokrice hydropower plant could start construction in 2027-28

Construction of Slovenia’s long-delayed Mokrice hydropower plant could begin in late 2027 or early 2028, subject to permitting and possible legal challenges. The project would complete the chain of hydropower facilities on the lower Sava River. It is designed...
Supported byVirtu Energy