Montenegrin coal-fired thermal power plant Pljevlja has been taken offline for scheduled annual maintenance, which should last from 18 April until 2 June.

Power utility EPCG said that this year’s overhaul plan includes maintenance of the boiler plant, replacement of a part of the boiler’s screen tubes, repair of damaged air heaters, overhaul of milling plants and equipment in the engine room, as well as revision of all valves and dampers, maintenance and testing of electrical equipment. The current version of the control system will also be updated. In total, the cost of maintenance works will be around 3.1 million euros.

EPCG Director for Energy Management Darko Krivokapic said that, thanks to good hydrological conditions in this part of the year, regardless of slightly lower rainfall averages in March and the first half of April, the power plant’s shutdown will not affect electricity supply in Montenegro.

Reservoir of HPP Perucica is at balance level, while the reservoir of HPP Piva currently has the potential to produce almost 100 GWh more electricity than planned. This should be enough to cover consumption needs mainly from own sources, without significant electricity imports.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Montenegro extends Sinjajevina wind project timeline to 2030

Montenegro has extended the development timetable for the 112 MW Sinjajevina I wind farm, moving the expected commercial operation target toward 2030. The revised schedule reflects ongoing permitting and grid infrastructure constraints. The project is located near Kolašin. Government annex...

Montenegro imports nearly 30% of 2025 electricity as renewables dominate output

Montenegro relied on imports for almost 30% of its electricity needs in 2025. The country covered almost 30% of its electricity requirements through net imports, indicating ongoing exposure to regional wholesale markets. Domestic generation remained largely renewable during the...

Montenegro imports nearly 30% of electricity needs in 2025

Montenegro relied on imports for almost 30% of its electricity needs in 2025, with net imports covering almost 30% of total electricity requirements. The figures point to continued exposure to regional wholesale markets alongside a largely renewable domestic generation...