Supported byClarion Energy
HomeElectricityMontenegro: TPP Pljevlja...

Montenegro: TPP Pljevlja set to resume production by 1 December after major overhaul

Coal-fired thermal power plant Pljevlja is expected to resume electricity production no later than 1 December, according to EPCG’s Director for Electricity Generation, Miro Vračar. He said that the plant’s start-up process is already underway and typically requires about ten days to complete.

Vračar explained that numerous systems installed during the facility’s ecological reconstruction must be synchronized and tested. If everything proceeds according to plan, the plant could be reconnected to the grid between 25 and 28 November. However, he stressed that 1 December remains the final deadline, barring unforeseen complications.

The power plant has been offline since 1 April, when the final stage of its environmental overhaul began. The prolonged shutdown has placed considerable financial pressure on EPCG, which has spent nearly 80 million euros on electricity imports during this period. As a result, the company posted a loss of more than 90 million euros by the end of the third quarter.

Under the contract with the reconstruction contractors, 1 December is the official deadline for completing the ecological upgrade and restarting operations. EPCG had previously sought a mid-November commissioning date in an effort to accelerate the work, but Vračar confirmed that all activities remain within the agreed timeline.

The reconstruction is being carried out by a Chinese-Montenegrin consortium consisting of DEC International, Bemaks, Permonte and BB Solar, under a contract worth 85.9 million euros including VAT.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

MMK Vilusi requests environmental screening for 35 MW solar plant in Nikšić

MMK Vilusi has applied for environmental screening for a 35 MW solar power project in western Montenegro, with the development planned for the Nikšić municipality. The request is described as an early regulatory step in the project’s permitting process....

Domestic industrial PPAs open new revenue opportunities for Serbian and Montenegrin renewables

Domestic industrial demand can support renewable investment and improve electricity cost predictability, but the carbon value of a power purchase agreement depends on the products being exported and the emissions rules governing them. Renewable developers in Serbia and Montenegro have...

Montenegro’s electricity exporters need stronger PPAs to secure Italian market revenues

The Adriatic interconnector gives Montenegro's renewable generators access to Italian buyers, but investment returns depend on carbon treatment, delivery profiles and the fallback provisions built into individual export agreements. Montenegro's electricity interconnection with Italy offers renewable energy investors access to...
Supported byVirtu Energy