Supported byClarion Energy
HomeSEE Energy NewsMontenegro: Power utility...

Montenegro: Power utility EPCG plans capacity increase in HPP Piva modernization project

The project for revitalization and modernization of hydropower plant Piva, under which the tender documentation for equipment procurement is in preparation, will significantly contribute to the extension of the operational life of this facility, said the statement from power utility EPCG.

Head of modernization of hydropower plants unit at EPCG, Bosko Bozovic explained that during the preparation of tender documentation two options are considered. In the first variant, the extent of modernization, in addition to turbine regulator and generator control system, includes the generator’s primary equipment (turbines and turbine equipment, generator equipment and block transformers). Thus, the power output of the plant will be increased.

The second variant does not include increasing the power output of the plant and generator’s primary equipment is excluded from the scope of the revitalization. The scope will be limited to replacement and modernization of the entire turbine control system and generator control system, while the revitalization of primary equipment would be carried out in some later stage of the project.

Bozovic added that, at the same time, project documentation for construction works which will include the revitalization of the dam and the construction of protective structures is being prepared as well.

EPCG adopted a decision on the revitalization of HPP Piva in 2007. The project involves the revitalization and modernization of hydro-mechanical and electrical equipment in order to extent the operational life of the plant by additional 30 to 40 years, transmits Serbia-energy.eu

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Southeast Europe power prices drop on Saturday, but evening peaks stay above €250/MWh

Electricity baseload prices fell by more than 20% across several Southeast European markets for Saturday delivery. Despite the decline, evening prices still rose above €250/MWh, indicating that flexibility remains priced into the most constrained hours. The day-ahead figures show...

Croatia extends winter price support for household electricity, gas and heating

Winter support period and budget allocation Croatia is spending about €170 million to keep household electricity, gas and heating costs below market levels during winter. The programme is designed to shield consumers from wholesale volatility while delaying a return to...

Kapino Polje solar complex expands EPCG generation near Nikšić to about 40 MW

Construction progress on L1, L2 and B1 sections Work has started on the Kapino Polje project near Nikšić, with activity under way on the L1, L2 and B1 sections. The combined scope for these sections represents around 20 MW. Support...
Supported byVirtu Energy