Montenegro: Masdar continues expanding investments in Montenegro

UAE Minister of Energy Sultan bin Saeed Al Mansoori said after the meeting with Montenegrin Minister of Economy Dragica Sekulic that the country has very favorable investment environment and significant energy sector potential. UAE-based renewable energy company Masdar has expressed interest in continuing and expanding its investments in Montenegro.
Krnovo wind farm has power output of 72 MW, and it is expected to produce between 200 and 230 GWh of electricity per year, which is about 8 % of the national output. The cost of the project was 120 million euros and it was partially financed through loans provided by the German KfW Bank and the European Bank for Reconstruction and Development (EBRD). The wind farm was put into operation in November 2017. In January 2018, UAE-based company Masdar acquired 49 % stake in Krnovo wind farm. French Akuo Energy holds the remaining stake.

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

EPCG completes major works on €26m Gvozd 2 wind expansion in Montenegro

Montenegro’s state power utility EPCG has completed most work on the second of three turbine foundations at its 21 MW Gvozd 2 wind project, advancing a nearly €26 million expansion further into construction. The project is located on the...

Perućica hydropower unit EPCG returns 190 MW after annual maintenance

Montenegro’s state power utility EPCG has returned 190 MW of capacity at the Perućica hydropower plant to operation after completing the main phase of its annual maintenance programme. The restoration brings additional generation capacity back online following the maintenance...

Montenegro’s renewable boom reaches the grid-connection test

Montenegro has accumulated a large pipeline of proposed solar and wind projects, but August reinforced that the decisive development constraint is shifting toward the transmission system. CGES and Nu Energy signed the grid-connection agreement for the Velestovo project, one of the country’s more advanced...