Montenegro, EPCG signed contract on the construction of district heating system in Pljevlja

Montenegrin state-owned power utility EPCG signed a contract with the Public Works Administration on the construction of district heating system in the city of Pljevlja.

The first phase of the project envisages the development of the main design of the heating system, as well as the construction of the main line in the length of 1,830 meters.

CEO of EPCG Nikola Rovcanin said that he expects that the works on the first phase will start by the end of the year, adding that the company will invest 5 million euros in the first phase.

In April, EPCG said that it has started the environmentally oriented reconstruction of the country’s sole coal-fired thermal power plant Pljevlja, with the aim of increasing the plant’s operational life. The project’s value is 70 million euros and it should be completed in two and a half years.

In June 2020, EPCG signed a contract for the reconstruction of coal-based thermal power plant Pljevlja with a consortium led by Chinese Dongfang Electric Company (DEC). The selected consortium offer to perform the reconstruction for around 54.4 million euros including VAT. EPCG later decided to invest additional 15 million euros in the reconstruction.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

EPCG completes major works on €26m Gvozd 2 wind expansion in Montenegro

Montenegro’s state power utility EPCG has completed most work on the second of three turbine foundations at its 21 MW Gvozd 2 wind project, advancing a nearly €26 million expansion further into construction. The project is located on the...

Perućica hydropower unit EPCG returns 190 MW after annual maintenance

Montenegro’s state power utility EPCG has returned 190 MW of capacity at the Perućica hydropower plant to operation after completing the main phase of its annual maintenance programme. The restoration brings additional generation capacity back online following the maintenance...

Montenegro’s renewable boom reaches the grid-connection test

Montenegro has accumulated a large pipeline of proposed solar and wind projects, but August reinforced that the decisive development constraint is shifting toward the transmission system. CGES and Nu Energy signed the grid-connection agreement for the Velestovo project, one of the country’s more advanced...
Supported byVirtu Energy