Montenegro: EBRD lends 28 million euros to CGES for substation upgrade

The European Bank for Reconstruction and Development is providing a sovereign-guaranteed loan of up to 28 million euros to Montenegro’s electricity transmission system operator CGES for the upgrade of the Brezna electrical substation.

-The project is highly significant as it will allow the integration of 400 MW of renewable energy into the national grid, helping the country decarbonise its economy. Moreover, it will reduce transmission losses by 13 GWh/year and secure a safe and reliable electricity supply in Montenegro as well as in the region by further strengthening the Trans-Balkan corridor which connects countries in the region to Italy and the EU – the EBRD said in a statement last week.

The project involves the installation of two power transformers and connecting them to the national grid via the new Lastva-Pljevlja transmission line. This will raise Brezna’s capacity to 400/110 kV, meaning that a large number of renewable energy power plants, that are now under development, can be connected with the substation, the statement read.

The Brezna substation is an important part of Montenegro’s transmission system as it connects the 400 kV Cevo-Pljevlja 2 transmission line with existing power grid to form a 400 kV ring. It also lays the groundwork for a prospective power link to Sarajevo, in neighbouring Bosnia and Herzegovina, which is an initiative in a preliminary planning stage, supported by the EBRD.

As part of the Brezna project, the EBRD and the European Union will provide capacity-building opportunities and create guidelines so that the regulators and other key local stakeholders can work effectively with CGES in making Montenegro’s electricity market a level playing field for renewable energy, according to the statement.

The EU is also providing a technical assistance grant of 1.05 million euros from the Western Balkans Investment Framework (WBIF) to develop the feasibility study, an environmental and social impact assessment and the preliminary design.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Domestic industrial PPAs open new revenue opportunities for Serbian and Montenegrin renewables

Domestic industrial demand can support renewable investment and improve electricity cost predictability, but the carbon value of a power purchase agreement depends on the products being exported and the emissions rules governing them. Renewable developers in Serbia and Montenegro have...

Montenegro’s electricity exporters need stronger PPAs to secure Italian market revenues

The Adriatic interconnector gives Montenegro's renewable generators access to Italian buyers, but investment returns depend on carbon treatment, delivery profiles and the fallback provisions built into individual export agreements. Montenegro's electricity interconnection with Italy offers renewable energy investors access to...

Montenegro construction permit issued for 88 MW Korita wind farm near Bijelo Polje

Montenegro has issued a construction permit for the 88 MW Korita wind farm near Bijelo Polje, moving the project towards implementation. The authorisation was granted following completion of planning and environmental approval procedures. The permit was issued to local...
Supported byVirtu Energy