Mintia gas plant commissioning progresses after 400 kV grid connection tests

400 kV connection energisation for first gas turbine unit

The Mintia gas-fired power plant has reached a key milestone in its commissioning following successful tests of the electrical infrastructure linking the facility to Romania’s national transmission network. Transelectrica said the testing included energisation of the 400 kV grid connection for the plant’s first gas turbine unit. The programme also covered activation of power transformers used for both grid integration and supply to the plant’s auxiliary internal systems. The works were completed on 15 June.

Inspections and operational verification continue

After the testing phase, engineers started additional technical inspections and operational verification procedures for the electrical equipment. These activities form part of ongoing commissioning work and reliability validation. The verification procedures are expected to continue over the coming weeks.

Project development and earlier grid connection acceleration

The Mintia power plant is among Romania’s largest new energy infrastructure investments, with an estimated development cost of approximately €1.4 billion. Earlier this year, Transelectrica accelerated grid connection works for the first 575 MW gas turbine unit. That step enabled the project to move into its latest phase of system testing and operational readiness.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania Competition Council clears NIS Petrol acquisition by Argenta

Romania’s Competition Council has approved the acquisition of NIS Petrol by Romanian company Argenta, removing a regulatory obstacle to NIS’s planned withdrawal from the Romanian market. The decision comes as pressure continues over the Serbian oil group’s Russian ownership....

Transelectrica completes €51 million STATCOM voltage control upgrade ahead of schedule

Romanian electricity transmission operator Transelectrica has completed a €51 million investment in voltage control infrastructure. The project is designed to strengthen the national grid’s ability to accommodate additional renewable generation and manage fluctuations in electricity flows. Transelectrica said the...

Romanian electricity demand down 4% in 2026 amid near-48% solar growth

Consumption trends across customer groups Romanian electricity consumption declined by 4% in the first eight months of 2026, according to data published by the National Institute for Statistics. Total electricity use reached 32.02 TWh between January and August, compared with...
Supported byVirtu Energy