€15 million steam-turbine upgrade progresses to commissioning

Croatian oil company INA has completed mechanical work on a €15 million steam-turbine upgrade at its Rijeka refinery. The project is now moving towards commissioning after the mechanical completion phase. The new installation uses back-pressure steam turbines equipped with generators.

The back-pressure design is intended to enable the refinery to recover more energy from steam already used in its industrial processes. INA said the turbines are part of an efficiency-focused upgrade within the refinery’s broader modernization programme.

Timeline for trial operation and commissioning

Mechanical completion was achieved at the end of August, around five weeks ahead of the contractual schedule. Trial operation and commissioning with process medium were scheduled to begin in September. This sequence keeps the project aligned with the planned transition from mechanical works to operational testing.

Once operational, INA expects the turbines to reduce steam consumption and lower internal energy costs. The company also expects additional electricity generation for use at the refinery.

Energy efficiency, emissions and regulatory alignment

Alongside changes in steam use and power generation, INA expects a corresponding decline in carbon dioxide emissions. The upgrade supports compliance with Croatia’s Energy Efficiency Act. It forms part of wider modernization efforts at Rijeka.

INA teams implemented the upgrade with external contractors, including Siemens Energy. The investment level was described as relatively small compared with the refinery’s broader modernization programme, while targeting persistent cost pressures tied to existing energy systems.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

INA outlines plan to lift Croatia gas output via new well commissioning

Five 2026 wells to reverse declining production Croatian oil and gas company INA expects domestic natural-gas production to rise by around 10% after five new wells are commissioned in 2026. The additional output is intended to reverse several years of...

Acciona Energia commissions 72 MW Croatian wind under 12-year contracts for difference

Acciona Energia has commissioned 72 MW of wind capacity in Croatia under 12-year contracts for difference, expanding its operating footprint as it develops large-scale solar. The commissioning brings the company’s Croatian operating portfolio to 102 MW across three wind...

Croatia amends Electricity Market Act to expand aggregation, grid studies, and connection rights

Croatia’s amended Electricity Market Act entered into force on October 15, 2026, introducing changes that go beyond conventional electricity-market reform. The legislation reshapes the commercial roles for industrial flexibility, the preparation of grid-connection studies, and the duration of legacy...
Supported byVirtu Energy