Greece, Trial operation of TPP Ptolemaida V reaches full capacity

The new, state-of-the-art thermal power plant owned by the Greek company Public Power Corp, PPC, TE Ptolemaida V has entered the final phase of testing ahead of official commissioning. The power plant is currently supplying electricity to the grid, gradually increasing capacity since the beginning of December without technical problems.

PPC’s Novo plant was delivering approximately 300MW by mid-December, almost half of its total capacity of 660MW, before increasing its grid input to 450MW last week. Then, as of December 18, the capacity reached 616 MW.

As is standard practice at the international level, new plants of this type go through three phases of trial testing. The first phase was implemented by the project developer, GEK TERNA.

TPP Ptolemaida V, a project worth over €1.4 billion, is expected to be ready for full commissioning by the end of February 2023. It will initially operate as a low-emission lignite-fired power plant before fuel conversion to natural gas.

Source: energypress.eu

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Greece approves €2.3bn programme for island grids, renewables and storage

Greece has secured approval for a €2.3 billion programme aimed at decarbonising its islands, with Athens directing more than €2 billion towards electricity interconnections, renewable generation and storage as it accelerates the replacement of oil-fired power. The approval was...

Metlen signs 10-year PPA for 12 MW Greek solar supply to Coca-Cola Tria Epsilon

Metlen Energy & Metals has signed a 10-year power purchase agreement to supply Coca-Cola Tria Epsilon with electricity from a new 12 MW solar project in Greece. The agreement is structured as a bilateral contract for long-term renewable power...

Greece wind buildout set to miss 2030 target despite faster 2026 additions

Greece accelerated wind-power construction in the first half of 2026, but projections indicate the country is still set to miss its 2030 capacity target. The outlook is based on figures cited in a document . Developers commissioned 321 MW...
Supported byVirtu Energy