Greece, RES needs investments in infrastructure

According to a study by the Institute of Energy for Southeast Europe (IENE), energy investments and reforms may take a major part of the Greek Recovery and Resilience Plan, but there is little attention granted to investing in renewable energy source (RES) hardware and infrastructure.

Among the projects to secure funding from the recovery plan are the growth and modernization of the national grid (307 million euros), that combined with energy storage (450 million euros) will lead to a robust grid that will support RES development.

However, according to IENE study, a major cause for concern is the absence from the Recovery and Resilience Plan of any subsidized investments in the Greek industry producing the equipment that is necessary for RES installation and in infrastructure. It would be crucial for this industry to play a supportive role to the construction of RES projects and act as a catalyst in the creation of local knowhow, employment and domestic added value, which in turn would reduce the importing of products and systems related to RES, and would strengthen exports.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Greece approves €2.3bn programme for island grids, renewables and storage

Greece has secured approval for a €2.3 billion programme aimed at decarbonising its islands, with Athens directing more than €2 billion towards electricity interconnections, renewable generation and storage as it accelerates the replacement of oil-fired power. The approval was...

Metlen signs 10-year PPA for 12 MW Greek solar supply to Coca-Cola Tria Epsilon

Metlen Energy & Metals has signed a 10-year power purchase agreement to supply Coca-Cola Tria Epsilon with electricity from a new 12 MW solar project in Greece. The agreement is structured as a bilateral contract for long-term renewable power...

Greece wind buildout set to miss 2030 target despite faster 2026 additions

Greece accelerated wind-power construction in the first half of 2026, but projections indicate the country is still set to miss its 2030 capacity target. The outlook is based on figures cited in a document . Developers commissioned 321 MW...
Supported byVirtu Energy