Eunice Energy has obtained an environmental permit for the installation of a 250 MW/1,000 MWh battery energy storage system in the Arcadia region. The battery storage system should help stabilize the electricity network in the region and allow the integration of more renewable generation capacity.

The facility will consist of 75 lithium-ion battery units covering a total area of roughly 112,157 square meters. The system will have a rated capacity of 292.9 MW/1,174 MWh and will be operated at 250 MW/1,000 MWh.

The project also envisages the installation of a new substation and overhead transmission lines. Eunice is developing the Arcadia project along with an identical project in Ptolemaida in Macedonia region. The two projects represent an investment of over 560 million euros

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Greece unveils €200 million battery storage scheme as project pipeline grows

Greece is preparing a €200 million battery-storage support programme as the country seeks to accelerate the deployment of standalone batteries and renewable-linked storage. The programme is expected to be implemented through four funding rounds before the end of 2026,...

Cyprus-Europe power link surveys resume amid Turkey-Greece maritime dispute

Greece is seeking to restart seabed surveys for the €1.9 billion Great Sea Interconnector, a proposed electricity connection between Cyprus and mainland Europe. The project’s implementation schedule has been affected by unresolved maritime disagreements with Turkey in the eastern...

Greece secures EU fiscal flexibility for nearly €1 billion in energy and resilience investments

Greece has secured European Union approval for additional fiscal flexibility covering nearly €1 billion in planned energy-security and resilience investments through 2028, creating greater budgetary room for battery storage, building efficiency and technologies aimed at reducing dependence on imported...