Greece: DEDDIE continues underground cable program to minimize wildfire risk

The Greek electricity distribution system operator DEDDIE is accelerating its program to place electricity cables underground, while the transmission system operator ADMIE focuses on connecting islands to the national electricity network. One of the primary motivations for burying cables is to prevent wildfires.

This week, DEDDIE announced the completion of an underground section near the town of Lavrio, southeast of Athens, and deactivated overhead cables that had previously passed through a protected forest area where a wildfire had occurred earlier this summer. The cables and pylons in this area will soon be removed.

DEDDIE reported that the underground sections of its electricity network now extend beyond 29,500 kilometers. The company has allocated a budget of €267 million, fully funded by the European Union’s Recovery and Resilience Fund, to continue expanding the underground cable network through 2030.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Cyprus-Europe power link surveys resume amid Turkey-Greece maritime dispute

Greece is seeking to restart seabed surveys for the €1.9 billion Great Sea Interconnector, a proposed electricity connection between Cyprus and mainland Europe. The project’s implementation schedule has been affected by unresolved maritime disagreements with Turkey in the eastern...

Greece secures EU fiscal flexibility for nearly €1 billion in energy and resilience investments

Greece has secured European Union approval for additional fiscal flexibility covering nearly €1 billion in planned energy-security and resilience investments through 2028, creating greater budgetary room for battery storage, building efficiency and technologies aimed at reducing dependence on imported...

HELLENiQ ENERGY commissions €50 million battery as Greece expands energy storage capacity

HELLENiQ ENERGY has commissioned a 100 MW/200 MWh battery energy storage system at its Thessaloniki industrial complex, marking a significant step in Greece’s shift from expanding renewable generation towards developing the flexible infrastructure needed to integrate it efficiently. Developed by...
Supported byVirtu Energy