Geotechnical work completed for REV Serbia's Brodarevo 1 and 2 hydropower sites

 

Energoprojekt Hidroinzenjering Co. Ltd. has completed geotechnical studies for Reservoir Capital Corp.’s 58.4-MW hydroelectric plant in Brodarevo, the company announces.

The Vancouver-based energy company commissioned Energoprojekt in 2009 to complete pre-feasibility studies for the hydropower project that includes two dam sites on the Lim River in southwestern Serbia.

Energoprojekt’s consultants drilled 24 holes of 12.5 meters and 108 meters in length and two galleries totaling 120 meters, excavated 11 pits, dug one shaft and completed 1,500 meters of seismic surveys in determining the area’s geological stability and permeability.

Brodarevo 1 will have a capacity of 26 MW, while Brodarevo 2 will have a capacity of 32.4 MW. Both will feature three turbines with an average flow of 150 cubic meters per second and four spillways, according to a Reservoir release.

Energoprojekt is now completing river diversion plans. Work on the project is expected to begin in spring 2012.

Previous article
Next article
Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania: SANY acquires 153 MW battery project as €1 billion investment plan advances

Chinese industrial group SANY has acquired a 153 MW standalone battery-storage project in Borzești, Romania, strengthening its position in the country’s expanding renewable-energy and energy-storage market. The project was acquired from RNV Infrastructure, part of the Renovatio Group, through the...

Greece: PPC and Metlen to commission first 300 MW of regional battery capacity in early 2027

Greek energy groups PPC and Metlen expect to commission the first 300 MW of their joint battery-storage portfolio in the first quarter of 2027, with the initial projects located in Bulgaria and Romania. The facilities will mark the first operational...

Slovenia’s Mokrice hydropower plant could start construction in 2027-28

Construction of Slovenia’s long-delayed Mokrice hydropower plant could begin in late 2027 or early 2028, subject to permitting and possible legal challenges. The project would complete the chain of hydropower facilities on the lower Sava River. It is designed...
Supported byVirtu Energy