EPS permits unlock €15.5 million Vrla 2 hydropower reconstruction near Surdulica

Serbia’s state-owned power utility EPS has obtained the necessary permits to start the reconstruction of HPP Vrla 2 near Surdulica in eastern Serbia. The project is linked to an investment valued at approximately €15.5 million, excluding VAT.

The reconstruction scope includes a full overhaul of the plant’s generating units, auxiliary systems, and hydromechanical equipment. Technical documentation for the works was prepared by Energoprojekt Hidroinženjering. The package covers civil, electrical, and mechanical designs, along with an environmental impact assessment.

Environmental approval for Vrla 2 documentation

The Ministry of Environmental Protection approved the environmental study related to the Vrla 2 reconstruction. The ministry also confirmed that no further review of the documentation is required. This approval supports the permitting status for the start of works at the site.

Vrla 2 part of Vlasina cascade modernization

The Vrla 2 reconstruction forms part of a wider modernization program for the Vlasina hydropower system. The program also covers the Vrla 1, Vrla 3, and Vrla 4 facilities. The stated program objective is to improve reliability, increase efficiency, and extend the operational lifetime of the cascade.

The broader rehabilitation effort began in late 2025, when EPS signed a contract with Energotehnika Južna Bačka. The refurbishment works under that agreement cover generating units, auxiliary systems, and hydromechanical equipment across the entire Vlasina cascade. The modernization program totals €109.7 million, with turbines and generators supplied by Andritz Hydro and Gamesa Electric.

EBRD loan and EU WBIF grant backing

The Vlasina modernization project is supported by international financial institutions. It includes a €67 million loan from the European Bank for Reconstruction and Development (EBRD).

The European Union has provided €15.4 million in grant funding through the Western Balkans Investment Framework (WBIF). This financing structure supports refurbishment activities across the Vlasina hydropower cascade, including Vrla 2.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

BHP moves to end options on eight Serbian exploration licences

BHP has issued termination notices for its Central Timok and Borsko exploration options in eastern Serbia, returning eight licences to Mundoro Capital when the notices take effect. The miner retains separate Trstenik and South Timok agreements, while Mundoro seeks partners to fund drilling on the returned licences.

Centerra proposes nearly C$4.1 million for 9.9% Mundoro stake

Centerra Gold has agreed to buy 12.374 million newly issued Mundoro Capital shares for approximately C$4.08 million (€2.60 million), in a proposed placement that would give it a 9.9% stake. The funding would support Mundoro’s exploration and working capital as it seeks partners for projects in Serbia, but the deal has not closed.

Northstone secures commitments for about EUR1.45 million Serbia placement

Northstone Resources secured commitments for a share placement worth about EUR1.45 million to fund exploration at its Tlamino gold-silver and Timok East copper-gold projects in Serbia. The financing will support drilling and technical studies, not mine construction.
Supported byVirtu Energy