Danube low flows cut Đerdap output and start tightening EPS thermal generation

Serbia’s EPS is facing higher reliance on power imports as Danube inflows remain persistently weak. The low-water conditions are limiting generation from the Đerdap hydropower cascade and starting to affect thermal output at Kostolac. EPS is a state-owned utility operating across both hydro and thermal assets.

Current Danube inflows are running at about half the long-term average and are approaching the river’s biological minimum. Forecasts provide little indication of a material recovery during the coming weeks.

Đerdap 1 output reduced under current river conditions

Đerdap 1 has recently generated slightly more than 5,000 MWh per day, which is around one-third of normal production. The reported daily volume equates to an average output of about 208 MW. Compared with an implied normal level of roughly 625 MW, the lost generation is close to 10 GWh per day.

Replacing the missing energy at wholesale prices of €100–130/MWh could cost approximately €1–1.3 million per day. The estimate excludes congestion effects, balancing requirements, and differences between hourly import prices. The financial impact increases further when low hydrology coincides with evening scarcity or regional heat-driven demand.

EPS said all refurbished Đerdap units remain technically available and are operating at the maximum output permitted by current river conditions. The constraint is therefore hydrological rather than mechanical. As a result, conventional improvements to availability do not address the underlying limitation.

Bajina Bašta pumped storage and Kostolac cooling constraints

The modernised Bajina Bašta pumped-storage plant provides some operational relief for EPS. EPS can buy electricity during low-priced solar hours, pump water into the upper reservoir, and generate during more expensive evening periods. This approach reduces replacement-energy costs but cannot fully offset sustained losses from the larger Đerdap cascade.

Low water levels are also restricting cooling capacity at the Kostolac thermal power plants. That limitation forces reductions in generation from the thermal fleet. With hydro output constrained at Đerdap while coal generation is affected at Kostolac, EPS faces a correlated risk across two parts of its production portfolio.

Shift toward imports and short-term trading pressure

Serbia’s electricity system remains operationally stable despite the generation constraints. However, the economic burden is moving toward imports, short-term trading, and careful use of stored hydro resources. The Danube drought has become a balance-sheet issue as well as a generation constraint.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

NIS operating window extends to 11 December 2026 amid uncertainty

Serbia’s crude supply chain remains dependent on temporary sanctions authorisations, with the operating window for NIS and corresponding JANAF activities extended to 11 December 2026. Uncertainty persists over MOL’s proposed acquisition of the Russian majority stake in NIS.

Serbia builds 1.5 bcm/year gas link as costs shape diversification

Serbia is expanding gas-supply options with a 1.5 bcm per year interconnector to North Macedonia under construction. The commercial value will depend on delivered costs, route reliability, storage and the expense of new infrastructure.

Romanian offshore gas growth puts export capacity in focus

Romania’s expected offshore gas production growth could leave additional supply discounted domestically unless cross-border capacity can move it to higher-priced markets. Capacity constraints could also increase the value of transmission upgrades and create recurring price spreads with Hungary and Serbia.
Supported byVirtu Energy