Capital overhaul of B2 unit of power planta TENT Nikola Tesla Obrenovac is about to be completed

 

Four month capital overhaul of TENT B2 unit is about to be completed. The unit b2 will be reconnected to the grid on 10th of September.

For the moment, all major overhaul works on B2 unit with 620 MW, are in accordance with planed dynamics, stated Mr.Ivan Gajic the head engineer for maintenance on TENT B power plants.

Major activity that influenced the time frame for this overhaul was the reconstruction of electrostatic precipitator ESP on B2 unit. Height of the ESP was increased for 2,2 meters which increased the effect of protection and decrease of emission of dust materials in accordance with domestic and European standards (50mg/Nm

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Southeast Europe enters 2026-27 winter short of flexibility

Southeast Europe faces a growing power-system flexibility shortage as grids, storage and dispatchable capacity lag behind project growth and rising volatility. Country-level pressures range from heavy imports in Serbia to negative prices in Croatia and faster battery deployment in Bulgaria.

Kosovo’s 260 MW B1 outage lifts winter import exposure

Kosovo enters its highest-demand months with the 260 MW B1 unit still unavailable, increasing reliance on electricity imports. The operator has not set a return date as regional prices and interconnector availability remain key variables.

Verbund signs PPA for Albania’s 72.6 MW Spille wind park

Austria's Verbund has signed a power-purchase agreement for the first project selected in Albania's first wind auction to reach construction readiness. Commercial operation is targeted for the first quarter of 2028.
Supported byVirtu Energy