Bulgaria’s Kozloduy nuclear power plant returned to full availability after Unit 6 reconnected to the grid following annual maintenance that began on 8 October. The restart adds about 1,000 MW of baseload capacity to the eastern Balkans as the heating season begins.
Fresh fuel was loaded for Unit 6’s next operating cycle, and the nuclear regulator issued a positive safety assessment before reconnection. The unit’s output is being raised step by step, while Unit 5 operated throughout the outage.
Kozloduy is Bulgaria’s only nuclear power plant. Units 5 and 6 are each rated at about 1,003 MW net, while Unit 6’s turbine generator has been upgraded to 1,100 MW. The plant produced 15.8 TWh in 2024, around 41% of Bulgaria’s electricity.
Price and supply effects
Bulgaria’s day-ahead electricity price fell about 19% for delivery on 18 November, then dropped a further 37.8% for Friday to €121.71/MWh. That was about €94/MWh below Austria’s price and €29/MWh below Greece’s.
Bulgaria had been a net electricity exporter on recent days, with scheduled flows into Serbia at about 241 MW on 18 November.
With both Kozloduy units online, Romania’s Cernavodă nuclear plant back and Mintia ramping up, the eastern Balkans are entering the first cold spell with significantly more firm capacity than a month earlier. The increased capacity is expected to cap Bulgarian and Romanian prices relative to Hungary and maintain northbound export flows that have supported Hungarian supply.
Fuel transition and expansion plans
Kozloduy is central to Bulgaria’s effort to diversify away from Russian nuclear fuel. Unit 5 began loading Westinghouse fuel in 2024 under a ten-year contract signed in 2022; a third batch was loaded during the unit’s outage in May–June this year.
Unit 6 still uses Russian fuel. Kozloduy applied in April to load six Westinghouse test assemblies into the unit, and licensing was still under way in September.
Bulgaria plans to expand the site with two AP1000 reactors, Units 7 and 8, each rated at about 1,250 MW gross. Westinghouse and Hyundai Engineering & Construction signed an engineering contract for the expansion in November 2024. The project targets Unit 7 for 2035 and Unit 8 for 2037.