Bosnia and Herzegovina: Ugljevik shuts down over coal shortage, Gacko offline after storm damage

Thermal power plant Ugljevik was forced to halt operations this morning due to a shortage of coal, the plant’s union president Boban Benović confirmed. He explained that severe weather had disrupted coal deliveries, leaving the facility without sufficient fuel to continue production. At this stage, there is still no clear estimate of when Ugljevik might return to the grid.

The Republic of Srpska’s largest electricity producer is facing deepening fuel-supply problems, compounded by the fact that mining has not yet started at the Ugljevik–Istok 2 deposit. This delay persists even though the RS Government has already paid most of the €125 million required to acquire Comsar Energy RS and the concession for coal extraction at the site previously owned by Russian businessman Rashid Serdarov. According to Benović, workers hope the situation will be resolved soon and expect the planned transfer of the concession to RiTE Ugljevik to move forward.

The difficulties come amid additional setbacks in the sector. The entity’s other thermal power plant, Gacko, was taken offline a day earlier, on 26 November. Director Maksim Skoko said the shutdown was caused by a failure in the coal-feeding system, triggered by recent storms. He added that the plant is expected to resume operations later in the day once repairs are completed.

These two outages underscore mounting challenges in the RS energy system, where unstable coal supplies and weather-related disruptions are increasingly affecting operational reliability.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Federation of Bosnia electricity generation up 15.8% in August as trade falls

Electricity production in the Federation of Bosnia and Herzegovina increased in August compared with August 2025, while both imports and exports declined from year-earlier elevated levels. Gross production reached 529 GWh, rising 15.8% from 457 GWh in August 2025....

Bosnia gross power generation rises in July on stronger exports

Bosnia and Herzegovina increased gross electricity production to 1,118 GWh in July, up from 1,082 GWh a year earlier. The higher output was supported by stronger hydro and renewable generation. Generation mix shifts with hydro and renewables Thermal plants accounted...

Elektrokrajina to invest €30 million in three-year distribution network reconstruction

Bosnian electricity distributor Elektrokrajina plans to invest about €30 million in a three-year reconstruction of its distribution network. The programme is designed to reduce losses and improve reliability across five cities and 16 municipalities. The works are intended to...
Supported byVirtu Energy