Supported byClarion Energy
HomeElectricityBosnia and Herzegovina:...

Bosnia and Herzegovina: RiTE Gacko reports return to profit with €290,000 net income in H1 2025

Coalmine and Thermal Power Plant (RiTE) Gacko reported a net profit of approximately 290,000 euros, a significant improvement compared to a loss of 11.8 million euros during the same period last year.

The company’s total revenues in the first half of the year reached 45.8 million euros, reflecting an 11.5% increase year-on-year. Meanwhile, total expenses decreased by 14% compared to the first half of 2024, amounting to 45.5 million euros.

In 2024, RiTE Gacko posted a net profit of around 720,000 euros, up from about 290,000 euros the previous year.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Federation of Bosnia electricity generation up 15.8% in August as trade falls

Electricity production in the Federation of Bosnia and Herzegovina increased in August compared with August 2025, while both imports and exports declined from year-earlier elevated levels. Gross production reached 529 GWh, rising 15.8% from 457 GWh in August 2025....

Bosnia gross power generation rises in July on stronger exports

Bosnia and Herzegovina increased gross electricity production to 1,118 GWh in July, up from 1,082 GWh a year earlier. The higher output was supported by stronger hydro and renewable generation. Generation mix shifts with hydro and renewables Thermal plants accounted...

Elektrokrajina to invest €30 million in three-year distribution network reconstruction

Bosnian electricity distributor Elektrokrajina plans to invest about €30 million in a three-year reconstruction of its distribution network. The programme is designed to reduce losses and improve reliability across five cities and 16 municipalities. The works are intended to...
Supported byVirtu Energy