Bosnia and Herzegovina, Electricity production at RiTE Ugljevik stable

Coalmine and thermal power plant (RiTE) Ugljevik, a subsidiary of state-owned power utility ERS, said that it has generated a total of 147.05 GWh of electricity in May, which is 1.4 % more than planned for the month.

In the first five months of the year, TPP Ugljevik was online for more than 2,326 hours, producing a total of 694.7 GWh of electricity in that period or 96.43 % of the planned amount.

In the first five months, TPP Ugljevik had two planned overhauls, as well as ten short unplanned outages, mostly due to pipe rupture in the boiler’s combustion chamber, which indicated that the complete piping system within the boiler has to be replaced soon.

RiTE Ugljevik recorded a net profit in the amount of some 180,000 euros in 2021, compared to a profit of 780,000 euros in 2020. The company’s operating revenues in 2021 increased by 5.7 % year-on-year and amounted to 77.2 million euros, while its operational expenditures rose by 7.8 % to 78 million euros.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Republika Srpska to raise electricity prices from 2027 amid Ugljevik coal issues

Businesses in Republika Srpska are expected to see higher electricity prices starting in January 2027, with households facing increases from March. The authorities are also seeking to strengthen the power sector’s finances while addressing coal supply problems that could...

Croatia electricity generation up 13% in August 2026, imports still high

August 2026 generation mix and year-on-year increase Croatia’s electricity production rose 13% year on year to 1,262 GWh in August 2026, according to figures from the Croatian Bureau of Statistics. The data show output increasing from 1,117 GWh in August...

Tolanovo 168 MW wind project enters concession process in Bosnia and Herzegovina

Concession launched for 168 MW Tolanovo wind farm The Republic of Srpska has opened a public concession procedure for the proposed 168 MW Tolanovo wind farm, with an estimated project value of €102 million. The development is located near Nevesinje,...
Supported byVirtu Energy