Bosnia and Herzegovina, Decrease in electricity production by 15% in October, to 1.1 TWh

The gross production of electricity in Bosnia and Herzegovina in October 2022 was 1,108 GWh, which is 15%, or 202 GWh less than in October 2021, when 1,310 GWh was produced, according to data from the BiH Statistics Agency (BHAS).

The drop in production in October is primarily due to poor hydrological conditions due to a prolonged drought. The thermal power plant Ugljevik has also been out of operation since the end of September due to overhaul.

In the total gross production, according to BHAS data, hydroelectric power plants participated with 27.7%, thermal power plants with 69.7%, and solar and wind power plants with 2.5%.

As a result of the drought, production from hydropower plants failed – it decreased from 356 GWh to 307 GWh on an annual basis, while production at thermal power plants decreased from 912 GWh to 773 GWh in the same period. Despite this, the share of production from thermal power plants remains high – 69.7%, which is unfavorable from the point of view of maintaining the balance in the power system, according to energy experts.

Electricity imports in October 2022 amounted to 398 GWh, compared to 319 GWh in October of the previous year. In the same period, exports decreased from 504 GWh to 474 GWh, according to BHAS data.

Source: bhas.gov.ba

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Republika Srpska accelerates generation and gas projects after drought curbs output

Energy and Mining Minister Petar Djokic said electricity production in Republika Srpska can normally run about 35% above domestic demand. He added that the buffer narrowed during summer due to dry weather cutting hydropower output. The Ugljevik thermal power...

Bosnia-Croatia southern gas interconnection delayed over financing and land issues

Agreement talks with AAFS Infrastructure & Energy Plans for the Southern Gas Interconnection between Bosnia and Herzegovina and Croatia remain delayed as developers work through financing, state-property and interstate-agreement issues. A planned agreement with US company AAFS Infrastructure & Energy,...

Bulgaria electricity generation up in June as demand declines

Bulgaria recorded higher electricity output in June while domestic consumption fell as the country moved into the summer period. Electricity production rose 3.4% from May to 3,162 GWh, while consumption decreased by 3.4% to 2,466 GWh. On a year-on-year...