Supported byClarion Energy
HomeElectricityBosnia and Herzegovina:...

Bosnia and Herzegovina: Bileća Lake water levels drop, but electricity supply in Republic of Srpska remains stable

The water level at Bileća Lake has fallen twelve meters below the planned level due to an unusually dry year. However, this shortfall does not pose a threat to electricity supply for consumers in the Republic of Srpska (RS), according to Ivan Koprivica, Executive Director for Technical Affairs at the ERS power utility.

Currently, the Trebišnjica hydropower complex (HET) has reached 76% of its seasonal generation target. HPP Višegrad is at 82%, while HPP Bočac on the Vrbas River has reached 90%, thanks to heavier rainfall in March.

Scheduled maintenance on all three Trebišnjica plants will begin in early September. HPP Višegrad and HPP Bočac are also scheduled for overhauls in the coming months.

Electricity supply to consumers in RS remains uninterrupted, despite occasional faults in the distribution network, which have been quickly resolved. However, electricity consumption increased by 8% between January and May 2025 compared to the same period last year, placing additional strain on ERS’s system.

To meet demand, ERS has been purchasing electricity on the open market at prices higher than its own production costs and selling it to consumers at lower rates. The drought has also limited electricity exports and increased domestic demand due to high temperatures.

On the coal-fired generation side, TPP Ugljevik has completed its overhaul and has been running smoothly for more than thirty days. Major maintenance at TPP Gacko is expected to finish by late July or early August, after which both plants will be fully operational, boosting electricity production in RS.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

ERS selects Hrgud consortium on nearly 82 million euros offer

Bosnia and Herzegovina’s ERS selected an El Promet-led consortium to build and finance the Hrgud wind farm under a fully financed 81.9 million euros offer. The utility chose it despite a rival construction bid that was 300,000 euros lower.

EBRD approves up to €46 million for Bosnia grid upgrades

Bosnia and Herzegovina’s transmission operator will use the approved financing to install four variable shunt reactors at selected substations. The equipment is intended to improve voltage control as renewable generation adds more variable power flows to the grid.

Nuclearelectrica targets 6 November restart for 700 MW Romanian reactor

Nuclearelectrica expects to reconnect Cernavoda Unit 1 on 6 November 2026 after more than three months offline because low Danube levels disrupted cooling-water supplies. Unit 2 is expected to remain offline until river conditions support both reactors operating simultaneously.
Supported byVirtu Energy