Biggest environmental project in serbian power gen sector, fgd solves the sulphur from power plants

 

By the end of 2011, the tender could be finished, the contract signed and the technology for the construction of flue gas desulphurization plant (FGD) selected in the Thermal power plant “Nikola Tesla” (TENT), all worth €248 million – said its director Petar Kneževic.

FGD plant TENT in Obrenovac will be the largest environmental project ever carried out in Serbia, and to be financed by Japanese loan, worth around €250 million, which earlier this year was agreed with that country.

The loan must be verified by the Government and then by the Parliament if these €250 million are to be approved. At the same time it’s been worked on the selection of consultants for establishment of procedures for tender- says  Kneževic.

Bidding will be open and all interested companies will be able to compete, Kneževic said, adding that, in parralel, the feasibility study and environmental impact made by the company „Energoprojekt“, Mining Institute  and the Faculty of Mechanical Engineering in Belgrade are being underway.

The money from the loan, as Kneževic expects, could be available immediately after the Serbian parliament approves it, that is by the end of 2011.

After that, in the first couple of months next year, tender for contractors and suppliers will be launched, and we can expect, at best, that the construction of the ecological plant starts in mid 2012- Kneževic concluded.

Environmental program TENT

Ecological modernization program, based on a study of environmental impact, lasts for 10 years and includes:

  • preparation of project documents
  • upgrade of electrostatic precipitators
  • change of ash transport and disposal systems
  • change of the wastewater management system
  • flue gas desulphurization
  • complete monitoring of emission and imission
  • implementation of  ISO 14.000 standard in the environmental management system

For the realization of ecological modernization it is necessary to provide €500 million, of which €300 million is for desulphurization. The second phase of ecological modernization includes reduction of nitrogen oxides (NOx) emission as well. This will be done by the reconstruction of boiler furnaces.

 

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbian renewable producers eye Italian electricity market as Montenegro corridor creates new export opportunities

Analysis by Virtu.Energy Serbian independent power producers (IPPs) could unlock additional long-term buyers, higher electricity revenues and improved project bankability by exporting electricity to Italy through Montenegro. However, the financial value of this route will depend on transmission costs, cross-border capacity...

Montenegro’s hydropower investment pipeline gains momentum as Perućica and Otilovići lead near-term spending

Montenegro’s most tangible hydropower investment commitments are concentrated in the modernisation of existing facilities and the development of smaller plants. An existing €40 million KfW financing package for Perućica and a €6.8 million construction contract for Otilovići provide the...

Serbia’s €2.6 billion Đerdap 3 project faces Danube water constraints and Romanian approval risks

Serbia’s proposed €2.6 billion Iron Gate 3 pumped-storage hydropower project is advancing through contracted technical preparation, but its long-term investment case will depend on securing a Danube operating regime that protects existing Serbian and Romanian hydropower facilities, as well...
Supported byVirtu Energy