Supported byClarion Energy
HomeElectricityAlbania: Electricity production...

Albania: Electricity production drops 31% in Q3 2025 as imports surge

Data published by the Albanian Institute of Statistics (INSTAT) shows that electricity production in the third quarter of 2025 reached 1,075 GWh, a decline of 31.3 percent compared to the same period in 2024, when output totaled 1,564 GWh.

Despite the drop in domestic generation, Albania increased its electricity exports. Outbound flows rose by 10.8 percent year-on-year to 312 GWh in the July–September period, while electricity imports surged by 65.3 percent to 1,260 GWh, reflecting the need to compensate for reduced hydropower output.

Hydropower plants remained the dominant source of electricity, providing 71 percent of total generation. State-owned hydropower plants produced 586 GWh, while privately owned facilities generated 312 GWh during the quarter.

Electricity consumption in Q3 2025 stood at 1,700 GWh, roughly unchanged compared with the same period last year. Network losses continued their downward trend, falling to 323 GWh, compared to 344 GWh recorded in the third quarter of 2024.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Croatia electricity generation up 13% in August 2026, imports still high

August 2026 generation mix and year-on-year increase Croatia’s electricity production rose 13% year on year to 1,262 GWh in August 2026, according to figures from the Croatian Bureau of Statistics. The data show output increasing from 1,117 GWh in August...

Albania: ALPEX electricity trading surges 76% in September amid regional market expansion

Electricity trading on the Albanian Power Exchange (ALPEX) increased sharply in September 2026, highlighting the continued development of organised wholesale electricity markets in Albania and the wider Southeast European region. Despite the strong annual growth, monthly trading activity declined...

Dalekovod secures €19.88 million contract for underground Tirana high-voltage substation

Contract award for Tirana Center substation Croatian power infrastructure company Dalekovod has secured a €19.88 million contract to develop a new underground high-voltage substation in Tirana, Albania. The facility is part of Southeast Europe’s expanding electricity transmission and distribution investment...
Supported byVirtu Energy