Electric Power Industry of Serbia announced on June 15th an international tender for the delivery of equipment and works on the rehabilitation of hydro power plant “Zvornik”, which is financed by loan funds of the German Development Bank (KfW). The deadline for submission is September 15th.

The total value of revitalization of HPP “Zvornik” is estimated at 95 million euros. 70 million euros derives from loan that KfW bank has approved, while the rest EPS will finance from its own resources. Part of the loan will be used for payments of works for which the tender was announced.

Modernization of HPP “Zvornik” includes the replacement of vital parts of “kaplan” turbine with increasing of diameter of the impeller, increasing efficiency, flow and power from 24 to 32.4 megawatts, and works on the drainage and cooling systems are also planned. Thanks to this loan, all four generators will be replaced, as well as block transformators, switchgear, while the command of the plant will be significantly enhanced due to new control system. Tender also predict collecting of data about facility and equipment, preliminary testing and dismantling of existing equipment, storage on construction site, as well as the reconstruction and rehabilitation of parts of the equipment which is retained for further exploitation.

Equipment design, making and testing of hydraulic turbine model, procurement of materials and equipment, manufacturing and testing of equipment in factories, packaging, transport and storage on the ground, insurance works and supplies, equipment installation, staff training, supply of spare parts, handover of plant and obligations during the period for removal of defects are also planned.

The aim of this project is to prolong the life of HPP

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

SEE electricity markets: Serbia leads regional prices as Hungarian-German spread widens and import dependence persists

Southeast European electricity markets remained under significant price pressure for delivery on 13 October, with Serbia recording the highest day-ahead price among the regional markets covered, while a widening premium between Hungary and Germany highlighted persistent constraints on electricity...

Romania reviews Doicești SMR after internal check leaves over 80% conditions unresolved

Romania’s nuclear power utility Nuclearelectrica is reassessing the future of the Doicești small modular reactor project following an internal review. The review concluded that more than 80% of the conditions linked to its February 2026 investment decision remained unresolved....

CGES approves €40 million grid deal for 488 MW Sinjajevina wind connections

High-voltage link for Sinjajevina 1 and Sinjajevina 2 Montenegro’s electricity transmission operator CGES has approved an arrangement covering approximately €40 million of high-voltage infrastructure to connect two wind farms with a combined capacity of 488 MW. The plan is aimed...
Supported byVirtu Energy