700MEUR for 600MW new power plant Ugljevik 3, contract signing expected soon

The executive director of Komsar Energy Republika Srpska, Sinisa Majstorovic expects the contract signing for new power plant Ugljevik 3 to be signed in july.

Majstorovic explained that the value of the investment is 700MEUR which is bigger amount that initialy planed, and added that the investor company is expecting to obtain location and construction permits in july as the the main design is completed.

He added that the time frame for new thermal power plant construction is 30 months from the contract signing date. Investor is working on the adjustments of complete documentation as the initial output power plan is changed and instead of 2x230MW, two new units of 300MW will be constructed.

According to Komsar energy the project will engage directly or indirectly few thousands of workers and after commissioning of the plant and its full operation the plant and mine itself will hire 600 new workers.

Source Vecernje novosti

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

CBAM verification raises costs and contractual risks for Southeast Europe’s electricity exporters

Electricity exporters and trading companies across Southeast Europe are facing growing pressure to demonstrate the carbon characteristics and physical delivery of electricity supplied to the European Union as the Carbon Border Adjustment Mechanism (CBAM) introduces additional costs, verification requirements...

CBAM widens Europe’s electricity price gap as carbon costs challenge Balkan exports

The European Union’s Carbon Border Adjustment Mechanism (CBAM) is reshaping electricity pricing and cross-border trading across Southeast Europe, widening the gap between wholesale power prices and the carbon-adjusted cost of electricity exported from the Western Balkans into the EU. The...

TAP expands gas supply capacity to Albania ahead of domestic network development

The Trans Adriatic Pipeline (TAP) has made 0.16 bcm/year of gas transport capacity available from Greece to Albania’s Roskovec exit point, expanding cross-border supply options before Albania has developed the domestic infrastructure needed to accommodate significant gas volumes. The additional...
Supported byVirtu Energy