Slovenia: NPP Krsko exceeds...

In September 2025, the Krsko nuclear power plant, jointly owned by Slovenia and...

Romania: Electrica completes 27...

Romanian electricity distributor and supplier Electrica has completed the construction of the Satu...

Romania: NEPI Rockcastle launches...

NEPI Rockcastle, the largest owner and operator of shopping centers in Central and...

Bulgaria: Bulgargaz secures LNG...

Bulgaria’s state-owned natural gas supplier Bulgargaz has completed a tender to meet part...
Supported byClarion Energy
HomeSEE Energy NewsHungary, No further...

Hungary, No further extensions were permitted and OAH requested the project company to submit supplementary application

The National Atomic Energy Office (OAH) said that the documentation submitted for the project for the expansion of nuclear power plant Paks by building two additional reactors is not convincing enough for the issuance of the implementation permit by the regulator.

The deadline for the issuance of the permit expired on 30 September. As it was already extended by three months, no further extensions were permitted and OAH requested the project company to submit supplementary application.

The statement from the OAH said that the documentation submitted is very thorough in many respects, but in order for the authority to be satisfied that all the requirements are fully met, further assessment and analysis are needed in some areas, taking into account the recommendations from the IAEA mission carried out in parallel with the licensing process. To this end, the OAH will order a further completion of the licensing procedure.

With this delay, it is very unlikely that the new units will be operational before 2030, when the permits for the operation of the two existing reactors expires. MVM, the plant’s operator, is already considering the extension of their operational life.

The delay also means that the Russian 10 million euros loan taken for the expansion project will have to be repaid starting from 2031 instead of 2026, thus decreasing its maturity by five years.

In January 2014, Hungarian Government has signed deal with Russia`s Rosatom, with a goal to increase output of the power plant, from current 2,000 MW to 4,400 MW by adding two more reactors. Under the agreement, Russia will provide 10 billion euros loan for the construction of new unit in existing NPP, which is around 80 % of estimated construction cost. According to initial plan, first unit was supposed to become operational in 2023.

Currently, NPP Paks provides about a half of Hungary’s total electricity generation and the new nuclear capacity will be even more significant following the closure of coal-fired TPP Matra.

Supported byOwner's Engineer banner

Recent News

Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Slovenia: NPP Krsko exceeds planned output in September 2025, begins scheduled overhaul

In September 2025, the Krsko nuclear power plant, jointly owned by Slovenia and Croatia, generated 449,426 MWh of net electricity, slightly exceeding the planned output of 446,000 MWh by 0.77%. On 28 September, NPP Krsko completed its 34th fuel cycle...

Romania: Electrica completes 27 MW Satu Mare 2 solar power plant to boost renewable energy portfolio

Romanian electricity distributor and supplier Electrica has completed the construction of the Satu Mare 2 solar power plant, further advancing its strategy to expand renewable energy production and diversify its portfolio. Located near Botiz in Satu Mare County, the new...

Romania: NEPI Rockcastle launches first solar power plant as part of €110 million green energy program

NEPI Rockcastle, the largest owner and operator of shopping centers in Central and Eastern Europe, has completed its first solar power plant in Chisineu-Cris, Arad County. The project is part of the company’s broader 110 million-euro renewable energy program...
Supported byVirtu Energy
error: Content is protected !!