Reservoir Capital Corp. is pleased to provide a progress report on its 58.4MW Brodarevo Hydroelectric Project on the river Lim in southwest Serbia.The Company has engaged Energoprojekt Hidroinzenjering Co. Ltd. (“Energoprojekt”) to prepare Feasibility Studies for both the Brodarevo 1 and Brodarevo 2 dams and power plants. These studies,as well as the various related studies being carried out under Energoprojekt’s supervision, are underway and progressing as detailed below.

Topography, sediment, erosion and hydrology studies have already been completed and testwork on the hydrological model is due for completion in June.

Geotechnical drilling for the dam foundations is scheduled for June and July, pending the completion of land purchases for the dam and plant sites and receipt ofthe relevant permits from the municipality.

The design, environmental studies and permitting for the sections of the M-21 road affected by the Brodarevo Project are expected to be completed by Put Inzenjering in late August.

Environmental studies in accordance with Serbian standards and legislation are being conducted in parallel with studies according to World Bank guidelines. Both sets of studies are scheduled for completion in late 2011.

Earlier this year, the Company received a one-year extension of the Brodarevo energy permits through January 2012 from the Serbian Ministry of Mines and Energy. The State Audit Commission has approved the Brodarevo Pre-Feasibility Studies and the Company intends to apply for a Building Permit once the Feasibility Studies are delivered to the relevant authorities.

Quality Control

Deputy Director of the Company’s operating subsidiary REV d.o.o., Milan Cusic, M.Sc. Dipl. Eng., a graduate of the Faculty of Mechanical Engineering of the University of Belgrade (1997) and previously Chief Hydro Engineer for Serbian State Utility EPS (2003-2010), is responsible for the preparation of the technical information in this release.

About Reservoir

Reservoir is a renewable energy company that is engaged in the development of a 58.4MW hydroelectric project at Brodarevo in southwest Serbia. Reservoir holds four geothermal exploration licenses in Serbia and has applied for three hydroelectric licenses on the Cehotina River in Bosnia (17.75MW) and one to develop a 32 MW project from an existing reservoir dam at Vrutci in Serbia. The Company also holds a portfolio of 8 precious and base metal exploration properties in Serbia that, subject to approvals, are to be spun-out into a separately listed company. Reservoir’s common shares trade on the TSX Venture Exchange (symbol “REO”) and on the Frankfurt and Berlin Exchanges (symbol “ROC”).

Neither the TSX Venture Exchange nor the Investment Industry Regulatory Organization of Canada accepts responsibility for the adequacy or accuracy of this release.

Source sys-con.com

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

SEE electricity prices surge as wind generation drops and Serbia becomes the region’s most expensive market

Southeast European day-ahead electricity prices rose sharply on Friday, with Serbia emerging as the region’s most expensive market as weaker wind generation, higher cross-border import requirements and persistent supply constraints pushed wholesale prices towards €280/MWh. Serbia’s SEEPEX market increased by...

Krško nuclear plant generates 487,438 MWh in September 2026, misses target

The Krško nuclear power plant, jointly owned by Slovenia and Croatia, produced 487,438 MWh of net electricity in September 2026. Output was 1.53% below the plant’s monthly production target for the month. The reported shortfall followed a plan to...

Kovačica wind complex expansion to 200 MW after €140m Pupin project

Serbia’s Kovačica wind complex is set to reach 200 MW of installed capacity after adding the Pupin wind farm. The 95.5 MW Pupin development is backed by a €140 million investment supported by international lenders and renewable energy developers....
Supported byVirtu Energy